Construction Photo
Album
Welcome!
Construction is well underway on the Hoover Dam Bypass Project: both the
Arizona and the Nevada Approaches are finished and construction on the Colorado River Bridge is steadily
progressing! Scroll down the page (or use the Quick Jump menu)
to see the most recent construction photos. As construction
continues, this page will be updated periodically to give you a quick
peek at the progress and on-going activities at the construction
site.
Click on any
thumbnail to view an enlarged
version of that photo.
Please note that you will need to use the Back button on your
browser to return to this page. If you prefer a higher
resolution image (300 dpi or more), you can also download these from
our site using the High Resolution link located below
each thumbnail. Please note that these higher resolution
images (which are provided in TIF format) will take longer to
download.
Quick Jump:
|
|
2008 Photos |
|
|
|
|
March 2008 |
|
|
|
Interim Surfacing Feb '08 |
|
|
|
February 2008 |
|
|
Interim Surfacing March '08 |
January 2008 |
|
2007 Photos |
|
|
December 2007 |
July 2007 |
|
|
November 2007 |
June 2007 |
March 2007 |
|
September/October 2007 |
May 2007 |
February 2007 |
|
August 2007 |
April 2007 |
January 2007 |
|
2006 Photos |
|
|
|
August 2006 |
April 2006 |
|
November/December 2006 |
July 2006 |
March 2006 |
|
October 2006 |
June 2006 |
February 2006 |
|
September 2006 |
May 2006 |
January 2006 |
|
2005 Photos |
|
|
December 2005 |
August 2005 |
April 2005 |
|
November 2005 |
July 2005 |
March 2005 |
|
October 2005 |
June 2005 |
February 2005 |
|
September 2005 |
May 2005 |
January 2005 |
|
|
Additional Images/Photos (Including
Arizona Approach and the live webcam.) |
|
|
|
Images from March 2008 |
|
Interim Surfacing on the Arizona &
Nevada Approaches...
|

looking south
Las Vegas Paving performing compaction of the asphalt pavement on
the Arizona approach portion of the project.
High Resolution TIF (14 MB)
|

looking south
Las Vegas Paving placing the first lift of asphalt pavement on the
Arizona approach portion of the project.
High Resolution TIF (14 MB)
|
|
Colorado River Bridge...
|

looking northwest
In Arizona, pre-assembled Arch reinforcing steel cages are
stockpiled and await placement as part of an Arch segment.
High Resolution TIF (14 MB)
|

looking west
View of underside of bridge spans 1 and 2 as seen from the existing
US93 hairpin in Nevada.
Working approximately 95 above the ground, an Obayashi / PSM, JV
worker attaches the temporary orange overhang falsework brackets to
the outside of the steel girder of span 2.
High Resolution TIF (14 MB)
|

looking east
View of spans 3 and 4 as seen from the deck of the bridge.
In the foreground, Obayashi / PSM, JV workers survey grade and
adjust the overhang falsework brackets on the outside of the steel
girder of span 2.
In the
background, Olsen Beal crews place stay
in-place decking for bridge span 3, between piers 3 and 4.
High Resolution TIF (14 MB)
|

looking southwest
Utilizing the south cableway crane system, Olsen Beal crews
transport and place steel stay in-place decking for bridge span 3,
between piers 3 and 4. Hanging on temporary supports between the
girders, the bridge deck drain piping system can be seen.
High Resolution TIF (14 MB)
|

looking southeast
View of the bridge alignment, looking from
Nevada towards Arizona.
In the foreground, crews from Steel
Engineers place reinforcing steel for the deck of span 1,
between Abutment 1 and Pier 1.
In the
background, Olsen Beal crews place stay
in-place decking for bridge span 3, between piers 3 and 4.
High Resolution TIF (14 MB)
|

looking southeast
View of the bridge alignment from the existing US93 hairpin in
Nevada looking towards Arizona.
In the foreground, Obayashi / PSM, JV workers place concrete for
Arch segment NV04-Left
In the background, across the Colorado River, the Arizona Arch
segments, along with Pier 14 columns are visible, approximately
1100 away.
High Resolution TIF (14 MB)
|

looking south
As seen from the existing US93 hairpin in Nevada, during a night
shift operation, a concrete pump truck delivers concrete to Obayashi
/ PSM, JV workers for placement at Arch segment NV04-Left.
High Resolution TIF (14 MB)
|

looking northwest
View of a pre-assembled reinforcing steel cage being delivered to
Arch segment NV03-Right from the Abutment 2 area in Arizona. This
25 long cage weighs approximately 32,000 pounds and is delivered
across the canyon with the south cableway crane system.
Visible just below the cage is the trolley assembly of the north
cableway crane system.
High Resolution TIF (14 MB)
|
|
Images from February 2008 |
|
Interim Surfacing on the Arizona &
Nevada Approaches...
|

looking southeast
View of the Arizona approach roadway prior to aggregate base
placement. On ramp B, near the Arizona interchange, Triple J
Trenching is visible excavating and installing conduits for future
electrical crossings.
High Resolution TIF (14 MB)
|

looking west
Triple J Trenching crews place and compact backfill material for
installation of conduits for future electrical crossings on the
Arizona approach.
High Resolution TIF (14 MB)
|

looking northwest
On the Nevada approach, Las Vegas Paving is hauling, placing, and
compacting aggregate base material onto the Nevada approach roadway
alignment near the Nevada interchange.
High Resolution TIF (14 MB)
|

looking west
View of a haul truck placing aggregate base material onto the Nevada
approach roadway alignment near the Hoover Dam Canyon Bridge.
High Resolution TIF (14 MB)
|

looking south
Las Vegas Paving shaping aggregate base material prior to compacting
on the Nevada approach roadway alignment.
High Resolution TIF (14 MB)
|
|
Colorado River Bridge...
|

looking east
The final span 2 steel girder is being transported from the abutment
1 area for placement in span 2. This girder is approximately 100
long and weighs 45 tons.
High Resolution TIF (14 MB)
|

looking north
Olsen Beal crews prepare cable rigging for hoisting and erecting
steel girders for the Nevada approach.
High Resolution TIF (14 MB)
|

looking west
Delivery of the steel girders for the Nevada approach.
High Resolution TIF (14 MB)
|

looking east
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) progress as seen from abutment 1 in Nevada.
Steel girders for span 1 are erected with 3 of the 4 placed for span
2.
Olsen Beal crews are transported in a man basket to pier cap 3 in
preparation for erection of the final girder for span 2.
High Resolution TIF (14 MB)
|

looking northwest
View of the Nevada approach columns with steel girders in span 2
erected along with 2 of the 4 girders erected in span 3.
At the bottom of Pier 5, the completed Arch is visible cantilevered
off of the NV skewback footing.
High Resolution TIF (14 MB)
|

looking northwest
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) progress as seen from downstream of Hoover Dam.
At the left, the Nevada approach columns (Piers 1, 2, 3, 4, & 5) are
visible with steel girders in-place for spans 1, 2, and 3. Near the
bottom of Pier 5, newly constructed Arch segments cantilever off of
the NV skewback footing.
To the right, the Arizona approach columns (Piers 14 & 15) can bee
seen with the girder placement completed. Below Pier 14, on the AZ
skewback, formwork cantilevers off of the footing.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from January 2008 |
|
Colorado River Bridge...
|

looking southeast
Olsen Beal crews look on as the North highline crane hoists a 50 ton
concrete certification weight.
High Resolution TIF (14 MB)
|

looking southeast
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman
Memorial Bridge) as seen from abutment 1 in Nevada.
Center The completed Pier 1 cap is awaiting steel
girder placement. System scaffolding encases the right column of
Pier 1.
Above the pier cap, the North highline crane is being certified
prior to use with a 50 ton concrete block test load.
High Resolution TIF (14 MB)
|

looking southeast
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman
Memorial Bridge) as seen from abutment 1 in Nevada. Both operational
highline cranes can be seen in their fully constructed
configuration.
Near the bottom of the photograph, piers caps for Piers 1, 2, 3, and
4 are visible.
High Resolution TIF (14 MB)
|

looking northwest
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) progress as seen from downstream of Hoover Dam.
At the left, the Nevada approach columns (Piers 1, 2, 3, 4, & 5) are
visible awaiting steel girder placement.
To the right, the Arizona approach columns (Piers 14 & 15) can bee
seen with the girder placement nearing completion.
Spanning the canyon above the Approaches, the 3 track cables of the
highline cranes are visible.
High Resolution TIF (14 MB)
|

looking south
The 50 ton concrete block test load
traverses the canyon via the north highline crane.
At
the left of the photograph, the Arizona approach is visible.
High Resolution TIF (14 MB)
|

looking north
Crews from Steel Engineers assembling arch reinforcing steel in a
template on the Arizona approach.
High Resolution TIF (14 MB)
|

looking southwest
Obayashi / PSM, JV field engineer performs construction surveying
from the existing US93 near the Nevada hairpin area.
High Resolution TIF (14 MB)
|

looking northwest
View of the assembled precast temporary stay cable towerhead. These
towerheads will be constructed on top of a 130 tall temporary tower
at Piers 5 and 14 as part of the cable stay erection system that
will support the arches until closure. At the completion of arch
construction, they will be removed along with the temporary stay
cables.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from December 2007 |
|
Colorado River Bridge...
|

looking southwest
View of the Nevada approach columns of the future CO River Bridge
(Mike O'Callaghan-Pat Tillman Memorial Bridge) as seen from the
existing US93 in Arizona.
From left to right:
In Arizona - Olsen Beal crews utilize a Manitowoc 2250
crane to assemble the trolley and attach the slack carriers for the
highline crane system
Piers 5, 4, 3, 2, 1 - columns are complete with their
pier cap visible above the cap falsework.
Abutment 1 can be seen to the far right.
In Nevada - Olsen Beal crews utilize a Manitowoc M250
crane to perform work on the Nevada side of the highline crane
system.
High Resolution TIF (14 MB)
|

looking south
At the NV skewback footing, Obayashi / PSM, JV crews assemble the
form traveler to its full configuration onto the left Arch rib in
preparation for construction of the third segment.
To the right of this picture, an additional crew assembles formwork
in preparation for construction of right Arch rib segment two.
High Resolution TIF (14 MB)
|

looking southeast
High above the roadway alignment in Nevada, Olsen Beal crews
continue construction of the new highline crane systems.
High Resolution TIF (14 MB)
|

looking south
Utilizing a Manitowoc M250 crane located in the abutment 1 area in
Nevada; Olsen Beal crews attach the slack carriers onto the 3
cables of the South highline crane system.
High Resolution TIF (14 MB)
|

looking northeast
In Arizona, steel girders make up a reinforcing steel fabrication
jig. On the exterior of this jig, iron workers will assemble Arch
segment reinforcing steel cages. Once complete, the cages will be
lifted off of the end of this jig and transported out to the form
traveler and placed as part of an Arch segment.
High Resolution TIF (14 MB)
|

looking southwest
In Arizona, high above the roadway alignment at Abutment 2, Olsen
Beal crews construct the highline crane system by attaching the
trolley and slack carriers to the 3 cables that span the canyon.
Below Pier 14, on the AZ skewback, formwork cantilevers off of the
footing in preparation for an arch segment concrete placement.
High Resolution TIF (14 MB)
|

looking northeast
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman
Memorial Bridge) as seen from downstream of Hoover Dam.
At the left, the Nevada approach columns (Piers 1, 2, 3, 4, & 5) are
visible awaiting steel girder placement. Near the bottom of Pier 5,
newly constructed Arch segments cantilever off of the NV skewback
footing.
To the right, the Arizona approach columns (Piers 14 & 15) can bee
seen with the girder placement completed.
The towers of the new highline crane system can bee seen to the edge
of the picture, along with their 3 cables spanning the canyon
between them.
High Resolution TIF (14 MB)
|

looking southwest
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman
Memorial Bridge) as seen from upstream of Hoover Dam.
Piers 15 and 14 appear to the left in this picture, while Pier 5, 4,
3, 2, 1 appear to the right.
Steel girders are in-place for the approach spans in Arizona while
crews construct the new highline crane system.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from November 2007 |
|
Colorado River Bridge...
|

looking north
In the contractors laydown yard, Obayashi / PSM, JV crews prepare
formwork to cast concrete panels for the exterior of the Arch strut
steel frames. A completed panel is hoisted by crane and transported
to the staging area, awaiting erection.
High Resolution TIF (14 MB)
|

looking west
In Nevada, Olsen Beal crews reeve cabling through an 18 part block
and tackle system for the backstay cable of the south highline crane
system.
High Resolution TIF (14 MB)
|

looking northwest
Nicholson Construction continue to drill through pipe sleeves and
nearly 60 into solid rock to install post tensioning strand for the
Arizona left temporary backstay anchor block.
High Resolution TIF (14 MB)
|

looking west
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman
Memorial Bridge) alignment as seen from the existing US93 hairpin in
Nevada.
Piers 4, 3, 2, 1 - columns are complete with their
pier cap visible above the cap falsework.
Abutment 1 can be seen to the far right. Beyond
Abutment 1, projects the towers of the twin highline crane systems.
Viewable high above the pier caps, the 3 diameter track cables for
the new highline system span the canyon between the Nevada and
Arizona highline towers.
High Resolution TIF (14 MB)
|

looking west
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman
Memorial Bridge) as seen from Arizona, looking towards Nevada.
In the foreground, steel girders span between Abutment 2 to Pier 15,
then from Pier 15 to Pier 14.
Across the canyon, the two white towers of the twin highline crane
systems can be seen in Nevada.
High Resolution TIF (14 MB)
|

looking south
View of half of the lower support structure of the form traveler
system as it is being prepared for installation onto the left Arch
rib in Nevada. This support structure forms the bottom of the Arch
segment while concrete is placed.
High Resolution TIF (14 MB)
|

looking west
In Nevada, Olsen Beal crews reeve cabling through an 18 part block
and tackle system for the backstay cable of the south highline crane
system.
High Resolution TIF (14 MB)
|

looking west
Utilizing a Manitowoc 2250 crane located in the abutment 2 area in
Arizona; Olsen Beal crews continue assembling the new highline crane
system.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from September & October 2007 |
|
Colorado River Bridge...
|

looking west
Utilizing a Manitowoc 2250 crane located in the abutment 2 area in
Arizona; Olsen Beal crews disassemble and prepare the S-70 Derrick
Crane for removal and demobilization.
High Resolution TIF (14 MB)
|

looking south
View of the new slack carriers awaiting installation on the highline
crane system.
High Resolution TIF (14 MB)
|

looking west
View of the completed Nevada towers for the new highline crane
system located at the abutment 1 area in Nevada. These towers are
335 tall.
High Resolution TIF (14 MB)
|

looking northeast
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman
Memorial Bridge) as seen from Arizona, looking towards Nevada.
At the right of the picture, red temporary bracing project out from
span 15 to form the deck overhang.
Across the canyon, a Manitowoc 2250 crane located at the Nevada
hairpin on existing US93 delivers materials and workers to the top
of Pier 5. Visible beyond it are the columns of the Nevada approach
and new highline crane towers.
High Resolution TIF (14 MB)
|

looking south
View of the Nevada approach columns as
seen from the crest of Hoover Dam.
From left to right:
Pier 5
At the top, Obayashi / PSM, JV personnel
stress the pier cap transverse post tensioning.
At the bottom, formwork projects
outward from the skewback footing, forming the first two segments of
the Arch.
Piers 4, 3,
2, 1 - columns are complete with their pier cap visible
above the cap falsework.
Abutment 1
can be seen to the far right. Beyond Abutment 1, projects the
tops of the twin highline crane systems.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from August 2007 |
|
Colorado River Bridge...
|

looking west
View of the erected steel girders for spans 15 and 16 as seen from
Abutment 2 in Arizona. The bridge deck elevation will be
approximately 9 above the girders top flange. In the background,
Olsen Beal erects the Nevada towers for the new highline crane
system.
High Resolution TIF (14 MB)
|

looking west
Obayashi / PSM, JV crews continue to construct overhang brackets and
formwork onto the edge of the span 16 girder.
Across the canyon, in the abutment 1 area in Nevada, Olsen Beal
crews erect the Nevada towers for the new highline crane system. To
the right of this picture, the Manitowoc 2250 crane located at the
Nevada hairpin on existing US93 is stored in its laid down, non-use
configuration.
High Resolution TIF (14 MB)
|

looking west
View of the Nevada approach columns of the future CO River Bridge
(Mike O'Callaghan-Pat Tillman Memorial Bridge) as seen from the
existing US93 in Arizona.
From left to right:
Pier 5 System scaffolding encases the right column
for concrete finishing operations. At the bottom of Pier 5, formwork
projects outward from the skewback footing, forming the first two
segments of the Arch.
Piers 4, 3, 2, 1 - columns are complete with their
pier cap visible above the cap falsework.
Abutment 1 can be seen to the far right.
High Resolution TIF (14 MB)
|

looking south
Utilizing a Manitowoc M250 crane located in the abutment 1 area in
Nevada; Olsen Beal crews erect the Nevada towers for the new
highline crane system. The one on the left is currently 240 while
the one on the right is 160 tall. When completed these towers will
top out at 335 in height.
High Resolution TIF (14 MB)
|

looking south
Obayashi / PSM, JV utilizing the S-70 Derrick Crane at Abutment 2 in
Arizona to remove the temporary bracing between piers 14 and 15
through an opening in the steel girder alignment. Once complete, the
final girder of span 15 will be set.
At the bottom left of this picture, crews continue to form the
foundation blocks of the Arizona towers for the new highline crane
system.
High Resolution TIF (14 MB)
|

looking west
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman
Memorial Bridge) as seen from Arizona, looking towards Nevada.
In the foreground, at the abutment 2 area, work continues on
construction of the foundation blocks of the Arizona towers for the
new highline crane system, along with the completion of girder
erection for spans 15 and 16.
Across the canyon, a Manitowoc 2250 crane located at the Nevada
hairpin on existing US93 delivers materials and workers to the top
of Pier 5. Visible beyond it are the columns of the Nevada approach.
High Resolution TIF (14 MB)
|

looking northeast
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman
Memorial Bridge) as seen from downstream of Hoover Dam.
At the left, the Nevada approach columns (Piers 1, 2, 3, 4, & 5) are
visible awaiting steel girder placement.
To the right, the Arizona approach columns (Piers 14 & 15) can bee
seen with the girder placement nearing completion.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from July 2007 |
|
Colorado River Bridge...
|

looking east
View of new stockpiled Cableway Crane cables located on the Nevada
approach awaiting erection.
High Resolution TIF (14 MB)
|

looking south
Nicholson Construction utilizing a Manitowoc M250 crane to transport
drilling equipment and materials to the location of the luffing guy
anchor block for the new Cableway Crane system near the Abutment 1
area.
High Resolution TIF (14 MB)
|

looking south
Utilizing the Manitowoc 2250 crane located at the Nevada hairpin on
existing US93, Olsen Beal crews construct falsework for the Pier 5
cap. Workers walk the steel beams situated 860 above the Colorado
River.
System scaffolding encases the columns of Pier 5 to allow access for
grouting and concrete finishing operations.
To the right of Pier 5, Pier 4 can be seen.
High Resolution TIF (14 MB)
|

looking south
Obayashi / PSM, JV utilizing the S-70 Derrick Crane and a yellow man
basket at Abutment 2 in Arizona to access the Pier 14 skewback
footing where crews continue to form Arch segments.
Above the man basket, the formwork for Pier 14 pier cap can be seen.
Concrete placement for this cap took place during the night time
hours on July 20, 2007.
To the left of Pier 14, completed Pier 15 along with its cap can be
seen.
High Resolution TIF (14 MB)
|

looking northwest
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman
Memorial Bridge) as seen from Arizona, looking towards Nevada.
Across the canyon, a Manitowoc 2250 crane delivers materials and
workers to the top of Pier 5. At the bottom of Pier 5, formwork
projects outward from the skewback footing, forming the first two
segments of the Arch. The blue formwork is the inner core of the
Arch form traveler system. This system will be utilized to form the
hollow inner portion of the Arch.
High Resolution TIF (14 MB)
|

looking southwest
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman
Memorial Bridge) as seen from the existing US93 hairpin in Nevada.
From left to right:
Pier 5 system scaffolding encases the columns for
grouting and concrete finishing operations. At the pier cap,
carpenters continue to set falsework.
Piers 4, 3, 2, 1 - columns are complete with their
pier cap visible above the cap falsework.
Abutment 1 can be seen to the far right.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from June 2007 |
|
Colorado River Bridge...
|

looking west
Olsen Beal crews erecting precast segments for Pier 14 left column.
Visible to the right and left are the completed columns of Pier 15.
High Resolution TIF (14 MB)
|

looking west
View of the formwork for the Pier 15 cap, ready for concrete
placement.
In the background, visible between Pier 15 columns, Olsen Beal crews
continue erecting precast segments for Pier 14 left.
High Resolution TIF (14 MB)
|

looking south
View of Piers 14 and 15 as seen from the crest of the Hoover Dam.
Olsen Beal crews utilizing the S-70 Derrick crane at Abutment 2 in
Arizona to transport precast segments and erect Pier 14 left column.
To the left of Pier 14, the completed columns of Pier 15 along with
the formwork for the cap can be seen.
High Resolution TIF (14 MB)
|

looking south
Olsen Beal utilizing the Manitowoc 2250 crane located at the Nevada
hairpin on existing US93 to erect precast segments for Pier 5 left
column.
High Resolution TIF (14 MB)
|

looking southwest
View of precast column segments, delivered to the Abutment 2 area,
in preparation for transport to their respective columns by the S-70
Derrick crane.
High Resolution TIF (14 MB)
|

looking south
View of the bridge alignment as seen from the crest of the Hoover
Dam.
Piers 15 and 14 appear to the left in this picture, while Pier 5, 4,
3, 2, 1 appear to the right.
High Resolution TIF (14 MB)
|

looking southwest
View of the delivered steel box girders, staged at the Abutment 2
area.
High Resolution TIF (14 MB)
|

looking north
Obayashi / PSM, JV continuing to assemble the inner core form of the
Arch form traveler system. This system will be utilized to form the
hollow inner portion of the Arch.
High Resolution TIF (14 MB)
|

looking north
Subcontractor, Nicholson, drilling holes for the rock anchors of the
new highline back stay anchor located in Arizona near abutment 2.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from May 2007 |
|
Colorado River Bridge...
|

looking east
Olsen Beal utilizing the S-70 Derrick crane at Abutment 2 in Arizona
to transport precast segments and erect Pier 14 right column.
Visible above Pier 14 is the completed columns of Pier 15.
High Resolution TIF (14 MB)
|

looking south
Olsen Beal utilizing the Manitowoc 2250 crane located at the Nevada
hairpin on existing US93 to erect precast segments for Pier 5 right
column.
Visible to the right of Pier 5 is the completed columns of Pier 4.
High Resolution TIF (14 MB)
|

looking west
View of the South temporary stay cable anchor block located in
Arizona near Abutment 2.
High Resolution TIF (14 MB)
|

looking southeast
View of the bridge alignment at abutment 1.
From left to the right
Completed Pier 2 can be seen with the formwork removed from its pier
cap. Pier 1 has the falsework in place waiting for reinforcing steel
/ formwork to construct the pier cap. The temporary stay cable
anchor blocks are visible in the roadway alignment to the right of
the abutment. Near the yellow Grove crane, the old Highline Crane
tower foundations are being prepared for removal by blasting.
To the left of the temporary stay cable anchor blocks, the
Pedestrian Access ramp zigzags up the mountainside from the future
access parking lot where the construction office trailers are
currently located.
High Resolution TIF (14 MB)
|

looking northeast
View of the bridge alignment looking towards Hoover Dam.
Left side of the picture
Completed Pier 2, 3, and 4. Pier 5 right / left columns are in
various stages of erection. Falsework for the Arch cantilevered off
of the Pier 5 skewback footing.
Right side of the picture
Falsework for the Arch cantilevered off of the Pier 14 skewback
footing. Pier 14 right / left columns are in various stages of
erection. The S-70 Derrick crane is setting precast segments for the
Pier 15 left column from Abutment 2. Pier 15 right column is
competed.
High Resolution TIF (14 MB)
|

looking northwest
View of the bridge alignment looking from Abutment 2 (Arizona)
towards Abutment 1 (Nevada).
Foreground: completed Pier 15 columns are wrapped in
scaffolding.
Background: Falsework for the Arch is cantilevered off of the
Pier 5 skewback footing. Above the falsework, Pier 5 can be seen
with crew erecting segments for the right column. Pier 4 is visible
with the pier cap falsework in place.
High Resolution TIF (14 MB)
|

looking northwest
Looking down at Pier 5 skewback footing on completed Arch segments
NV01 Right and Left. The falsework for segments 2 projects out over
the canyon, ready for formwork / reinforcing steel placement.
High Resolution TIF (14 MB)
|

looking northwest
View of the bridge alignment looking from Abutment 2 (Arizona)
towards Abutment 1 (Nevada) from above Abutment 2.
Foreground: Excavations for the temporary stay cable anchor blocks
are visible in the roadway alignment near the footing of the S-70
Derrick crane. The crane is currently setting precast segments for
the erection of Pier 15 left column.
Background: Pier 5 and the Arch segments in various stages of
construction. Next are the completed Pier 4, 3, 2. Pier 1 that can
be seen with the falsework in place for the pier cap construction.
Abutment 1 is visible behind Pier 1.
High Resolution TIF (14 MB)
|

looking northwest
Looking down on Olsen Beal crews preparing to set the next precast
segment at Pier 5 right as they work 230 feet above the skewback
footing.
Visible below are the completed Arch segments NV01 Right and Left
along with the falsework for segments 2.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from April 2007 |
|
Colorado River Bridge...
|

looking east
Olsen Beal utilizing the S-70 Derrick Crane at Abutment 2 in Arizona
to transport precast segments and erect Pier 15 right and left
columns.
Visible below Pier 15 is the skewback footing of Pier 14 with the
falsework for the Arch protruding outward.
High Resolution TIF (14 MB)
|

looking west
View of the South temporary stay cable anchor block located in
Nevada near Abutment 1.
High Resolution TIF (14 MB)
|

looking west
View of delivered concrete being cooled with liquid Nitrogen prior
to placement for construction of the Arch segment NV01-RT.
High Resolution TIF (14 MB)
|

looking southwest
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman
Memorial Bridge) alignment as seen from the existing US93 hairpin in
Nevada.
Abutment 1 in final stages of construction with the blockouts for
the tie back anchors remaining to be filled.
Pier 1 is shown with falsework for the pier cap in
place.
Pier 2 can be seen with the completed pier cap.
Pier 3 is visible with the completed pier cap along
with climbing scaffolding surrounding the columns.
Pier 4 is visible with the completed pier cap.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from March 2007 |
|
Colorado River Bridge...
|

looking west
Workers from Jakes Crane prepare for the removal of the counter
weights from the
Link Belt TG1900
erected on the Pier 15 left foundation. This worker is attaching
hoisting slings onto the weights wile perched nearly 865 above the
Colorado River.
High Resolution TIF (14 MB)
|

looking south
Obayashi / PSM,
JV utilizing a Manitowoc 2250 crane to construct / access Piers 3
and 4 from the Nevada
hairpin on existing US93.
High Resolution TIF (14 MB)
|

looking west
View of the bridge alignment as seen from
Arizona towards Nevada.
Piers 1, 2, 3,
4, 5 in various stages of completion. Formwork for Arch segments
NV01N and NV01S can be seen cantilevered off of the Pier 5 (NV
skewback) footing.
High Resolution TIF (14 MB)
|

looking southwest
Jakes Crane utilizing the S-70 Derrick
Crane at Abutment 2 in Arizona to dismantle the Link Belt
TG1900 from the Pier 15 left foundation.
Visible to the
left of the crane is Pier 15 right in partial stage of completion.
High Resolution TIF (14 MB)
|

looking north
Crane close-up.
High Resolution TIF (14 MB)
|

looking north
Workers from Jakes Crane utilizing the S-70 Derrick Crane at
Abutment 2 in Arizona to dismantle the
Link Belt TG1900
from the Pier 15 left foundation. Crews are removing the boom
section and transporting it to the laydown area on the Arizona
approach roadway.
High Resolution TIF (14 MB)
|

looking east
View of the future CO River Bridge (Mike
|