Construction Activities
What's Happening On the Job?
The Federal Highway Administration (FHWA) awarded a $7 million
surfacing project to
Las Vegas
Paving Corporation of Las Vegas Nevada in December 2007. The
paving project includes over 60,000 tons aggregate base, 45,000 tons
hot asphalt concrete pavement and nearly 18,000 lineal feet of
guardrail. The project is complete.
This project was accelerated in order to finalize paving and
guardrail throughout a majority of the Bypass Approach roadways and
take advantage of current construction materials prices and minimize
any future increases that may result from delays associated with the
contractor’s crane collapse that occurred during construction of the
River Bridge. Advancing this roadway surfacing project ensured
continued progress on the Bypass and minimized the remaining work to
be done after the River Bridge is completed – with the ultimate goal
of expediting the final opening of the Bypass.
Once the River Bridge nears completion, a final contract will be
awarded to pave the short sections of remaining roadway and the
roadway tie-ins at U.S. 93, as well as complete final signing,
striping, barrier, and pedestrian facilities. It is estimated that
this final contract will cost approximately $8 million and will be
advertised in late 2009. The total cost to complete the Hoover Dam
Bypass remains unchanged at $240 million and is consistent with the
original 2001 estimate.
The construction contract for the Colorado
River Bridge, was awarded to the joint venture
partnership of
Obayashi
Corporation and PSM Construction USA, Inc., in October of 2004 for
$114M. Construction began in early 2005 and is expected to be
completed in 2010. When completed, the 2,000 foot-long Colorado
River Bridge will span the Black Canyon (about 1,600 feet south of
the Hoover Dam), connecting the Arizona and Nevada Approach highways
nearly 900-feet above the Colorado River. The construction
requirements and challenges are as difficult as any in the world.
As of November 2008, the joint venture contractor has completed over
$78M worth of construction. Major milestone work complete includes
the abutments, approach columns, girders and deck, and arch skewback
footings. A number of the arch segments have been cast using a
temporary form traveler system. The contractor has established a new
cableway system developed specifically for this project and site.
The cable crane system spanning the canyon delivers materials and
equipment used in constructing the bridge. Other completed work
includes the precast segments for the bridge columns which will
support the roadway on the arch. The arch is now almost 40%
complete, and on track for closure in the third quarter of 2009.
Upcoming work will include continued of the cast-in-place concrete
arch over the Colorado River. Completion of the arch requires
construction of temporary stay towers which will support the arch
until it is closed in the middle. This is scheduled for September
2009.
.jpg)

Another milestone in the construction of the Hoover Dam Bypass was
completion of phase two, the Nevada
Approach project in November 2005. Edward Kraemer & Sons,
Inc., the contractor for the Nevada Approach project, completed this
$30.1 million roadway improvement from Nevada U.S. 93 to the new
Colorado River Bridge crossing nearly two months ahead of schedule.
Construction of the Nevada Approach, began in October 2003, and
within its short 24-month duration, the contractor constructed 2.11
miles of new four-lane highway alignment including six new bridges,
a new traffic interchange at U.S. 93 near the Hacienda Casino,
retaining walls, wildlife crossings, and a 1.6 mile extension of the
River Mountain River Loop hiking trail. To accomplish this feat, the
contractor moved over 1.5 million cubic yards of blasted rock
material, placed 2.8 million pounds of reinforcing steel, and poured
over 12,000 cubic yards of structural concrete.
Phase One of the Bypass was
finished in December 2004. Completion of the Sugarloaf Mountain
Bridge signified the end of construction on the
Arizona Approach project. The
project involved
building
a connection between U.S. 93 and the Colorado River Bridge. Major
components of the $21.5 million project include nearly two miles of
four-lane roadway, a 900-foot bridge on the east side of Sugarloaf
Mountain,
a
new traffic interchange at U.S. 93 and Kingman Wash Road, wildlife
crossings, trail access parking, improved drainage and rock
staining. The joint venture contractor, R. E. Monks Construction and
Vastco Inc, were responsible for construction activities on the
Arizona Approach. The project was completed on time.
Statement from the Federal Highway
Administration - November 24, 2008
The Federal Highway Administration extends its deepest sympathy to
the family of the construction worker who suffered a fatal accident
on the Hoover Dam Bypass project site today. The FHWA will work
closely with U.S. Department of Labor’s Occupational Safety and
Health Administration and the Joint Venture contractor, Obayashi
Corporation and PSM Construction USA, Inc., to determine the cause
of the accident. The accident occurred during a routine operation to
adjust a cable used to align the temporary concrete towers that
support construction of the twin arches. In the interim, all related
activities involving the area where the accident occurred are
suspended until further notice. Update: As of
Monday, December 1, 2008, all construction activities have resumed.
Contact: Nancy Singer, FHWA Public Information Officer, at
202-366-4650
Come inside the Construction Zone!
Be sure to check out photos of all our projects in our
Construction Photo Album.
Images are updated periodically. April 2009 photos showing the
progress of the Colorado River Bridge, as well as of the
Interim Paving Project (on both the Arizona and Nevada sides) are now posted!

Construction Schedule:

Web Cam:
Construction Web Cam - Our web cam is up and
running! Through the use of our interactive web cam, you can view
live-images of the Colorado River Bridge construction area, zoom in and out on specific
locations, e-mail images to someone, and post your own images to a
photo album. To be redirected to our webcam, all you have to do is
click on the camera in the top left side of any page, or just click here:
Hoover Dam
Bypass Web Cam. (Please note, some internet browsers will need
the pop-up blocker turned off in order to be redirected to the web
cam.)

|