|
Hoover Dam Bypass Marks Another
Milestone:
Project Awarded to Surface Majority of Bypass
Approach Roadways
The
Federal Highway Administration (FHWA) has awarded a $7 million
surfacing project in order to finalize paving and guardrail
throughout a majority of the Bypass Approach roadways. This paving
will be complete in Summer 2008.
This paving has been accelerated in order to take advantage of
current construction materials prices and minimize any future
increases that may result from delays associated with the
contractors crane collapse that occurred during construction of the
River Bridge. Advancing this roadway surfacing project ensures
continued progress on the Bypass while minimizing the remaining work
to be done after the River Bridge is completed – with the ultimate
goal of expediting the final opening of the Bypass.
The contract for this work was awarded to
Las Vegas Paving Corporation of Las Vegas Nevada. The
paving project will include over 60,000 tons aggregate base, 45,000
tons hot asphalt concrete pavement and nearly 18,000 lineal feet of
guardrail.
Once the River Bridge nears completion, a final contract will be
awarded to pave any remaining roadway and the roadway tie-ins at
U.S. 93, as well as final signing, striping, and barrier. It is
estimated that this final contract will cost approximately $8
million and will be advertised in late 2009. The total cost to
complete the Hoover Dam Bypass remains unchanged at $240 million and
is consistent with the original 2001 estimate.
Revised Schedule
A revised
schedule for completion of the Hoover Dam Bypass project has been
finalized. While still under development, the overall schedule and
opening of the bypass will be delayed about two years until late
2010. There are a number of alternatives under consideration that
could shorten the schedule by a few months. For details, see
our Schedule page. The project team looks forward to completing the Hoover Dam Bypass.
The project will reduce congestion, improve highway safety, and
provide security to dam operations and visitors.
Please continue to visit this
website for updates on the Hoover Dam Bypass. You can also visit
the newly activated web cam to view live images of the
construction area. In the upper left-hand margin, just click on the “web
cam” icon.
|