PLEASE TURN OFF POP-UP BLOCKERS TO VIEW WEB CAM

 

 

What's New


Colorado River Bridge Project Progressing Across Canyon

The joint venture contractor building the River Bridge, Obayashi Corporation and PSM Construction USA, Inc., is advancing construction of the 1,060 foot twin-rib concrete arch. The JV completed the design, fabrication and erection of the new highline system in January 2008. The system was developed specifically for this site and project requirements. Re-establishing the cableway system was a critical milestone to complete the project. Recently, the Contractor completed construction of steel tub girders and deck on the approach spans, and cast the first several segments at the end of each arch using a traveling form system. Upcoming work includes erecting two precast, segmental temporary towers at the ends of the approach span decks to anchor the cable support system for continued arch construction. Construction of the arch is expected to take approximately 14 months with completion scheduled in September 2009. Once the arch is complete and self-supporting, the cables and tower will be removed, and columns, pier caps and deck structure will be built on top of the arch completing the roadway.

Paving Contract Complete

The fourth phase of the Hoover Dam Bypass project is complete. The interim surfacing project was awarded to Las Vegas Paving Corporation in December 2007 was completed in June 2008. The project includes asphalt paving and guardrail on approximately 75% of the approach project length. Completion of the project minimizes the amount of remaining work to be done after the River Bridge is completed. The final project to open the bypass will include the short sections of remaining roadway tie-ins to the River Bridge and U.S. 93, as well as signing, striping, barrier, and pedestrian facilities on the entire bypass.
 

 

 

Web Cam & Continuing Construction Activities

  • As construction activities progress on the Colorado River Bridge, we take you right to the action with the use of our new interactive web cam.  Be sure to check it out by clicking on the web cam icon at the top left-hand side of the page.  Also, don't forget that we will periodically update the Construction Photo Album page with a few of our favorites that we took on-site.  September 2008 photos of the Colorado River Bridge are now posted!  In addition, April & May 2008 photos of the Interim Surfacing project on both the Arizona and Nevada Approaches are also available.
  • Construction of the Nevada Approach Project is now complete!  Check out photos of the complete alignment on the Construction Photo Album page. Older photos, including those from the completed Arizona Approach Project, can also be found through links on that page.   
  • Don't forget -- you can always find more information on our project by reading the latest newsletter on-line, via the Informational Material page.  Issue #16 - March 2008 - is now posted!

Old News ...
As we update the information on this page, the older information will be moved to another location.  Please click on the button to the left to access the previous What's New postings.

 

Schedule Update

Track progress on the project schedule here.

   

Last Updated: 11/10/2008

 
 

Copyright © 2002 CFLHD & HDR. All Rights Reserved. Web Design by - HDR, Inc.