Construction Photo Album
Welcome! Construction
is now complete on the Hoover Dam Bypass Project: both the Arizona and the
Nevada Approaches are finished and construction on the Colorado River Bridge was
completed in October! Scroll down the page (or use the Quick Jump menu) to
see our construction photos.
Click on any thumbnail to
view an enlarged
version of that photo. Please
note that you will need to use the Back button on your browser to return
to this page. If you prefer a higher resolution image (300 dpi or more),
you can also download these from our site using the High Resolution
link located below each thumbnail. Please note that these higher
resolution images (which are provided in TIF format) will take longer to
download.
Quick Jump:
|
|
2010 Photos |
|
Interpretive Plaques |
August 2010 |
April 2010 |
Dedication Activities |
Bridge Construction
(time lapse video) |
March 2010 |
October 2010 |
June/July 2010 |
February 2010 |
September 2010 |
May 2010 |
January 2010 |
|
2009 Photos |
|
December 2009 |
|
April 2009 |
November 2009 |
August 2009 |
March 2009 |
October 2009 |
June 2009 |
February 2009 |
September 2009 |
May 2009 |
January 2009 |
|
2008 Photos |
|
December 2008 |
|
|
November 2008 |
June 2008 |
Interim Surfacing March '08 |
October 2008 |
Interim Surfacing May '08 |
March 2008 |
September 2008 |
May 2008 |
Interim Surfacing Feb '08 |
August 2008 |
Interim Surfacing April '08 |
February 2008 |
July 2008 |
April 2008 |
January 2008 |
|
2007 Photos |
|
December 2007 |
July 2007 |
|
November 2007 |
June 2007 |
March 2007 |
September/October 2007 |
May 2007 |
February 2007 |
August 2007 |
April 2007 |
January 2007 |
|
2006 Photos |
|
|
August 2006 |
April 2006 |
November/December 2006 |
July 2006 |
March 2006 |
October 2006 |
June 2006 |
February 2006 |
September 2006 |
May 2006 |
January 2006 |
|
2005 Photos |
|
December 2005 |
August 2005 |
April 2005 |
November 2005 |
July 2005 |
March 2005 |
October 2005 |
June 2005 |
February 2005 |
September 2005 |
May 2005 |
January 2005 |
|
Additional Images/Photos (Including Arizona Approach.) |
Interpretive
Plaques
|
Dedication Plaque Final
|
Hoover RB Balustrade Plaque Final
|
Panel 1.1
|
Panel 1.2
|
Panel 1.3
|
Panel 1.4
|
Panel 1.5
|
Panel 1.6
|
Panel 1.7
|
Panel 1.8
|
Panel 1.9
|
Panel 2.1
|
Panel 2.2
|
Panel 2.3
|
Panel 2.4
|
Panel 2.5
|
Panel 3.1
|
Panel 3.2
|
Panel 4.1
|
Panel 4.2
|
Panel 4.3
|
Panel 4.4
|
Panel 4.5
|
Panel 5.1
|
Panel 5.3
|
RB Sidewlk Monuments
|
Dedication Activities
|
Arizona Governor Jan Brewer addressed the attendees at the Dedication of the
Mike O’Callaghan-Pat Tillman Memorial Bridge.
High
Resolution JPG
|

Nevada Congresswoman Dina Titus gave her remarks at the Dedication of the Mike
O’Callaghan-Pat Tillman Memorial Bridge.
High
Resolution JPG
|
Nevada Senator Harry Reid spoke at the Dedication of the Mike O’Callaghan-Pat
Tillman Memorial Bridge.
High
Resolution JPG
|

Federal Highway Administration Administrator Victor Mendez welcomes guests to
the Dedication of the Mike O’Callaghan-Pat Tillman Memorial Bridge (seated left
to right: NV Congresswoman Dina Titus, NV Senator Harry Reid, and Secretary of
Transportation Ray LaHood).
High
Resolution JPG
|
Secretary of Transportation Ray LaHood spoke to the guests at the Dedication of
the Mike O’Callaghan-Pat Tillman Memorial Bridge.
High
Resolution JPG
|

Nevada Senator Harry Reid gave his remarks at the Dedication of the Mike
O’Callaghan-Pat Tillman Memorial Bridge (seated left to right: FHWA
Administrator Victor Mendez, NV Lt. Governor Brian Krolicki, and AZ Governor Jan
Brewer).
High
Resolution JPG
|
Distraction, an all-girl group from Kingman, AZ sang the National Anthem at the
Dedication of the Mike O’Callaghan-Pat Tillman Memorial Bridge.
High
Resolution JPG
|

Nellis Air Force Base Honor Guard performed the presentation of colors at the
Dedication of the Mike O’Callaghan-Pat Tillman Memorial Bridge.
High
Resolution JPG
|
Leroy Spotted Eagle, Spiritual Leader of the Southern Paiute people performed
the blessing on the Mike O’Callaghan-Pat Tillman Memorial Bridge.
High
Resolution JPG
|

The Red Hand Dancers performed an intertribal dance, blessing the new Mike
O’Callaghan-Pat Tillman Memorial Bridge and project area.
High
Resolution JPG
|
The families of Mike O’Callaghan and Pat Tillman were honored at the Dedication
of the Mike O’Callaghan-Pat Tillman Memorial Bridge.
High
Resolution JPG
|

Hoover Dam Bypass Project Manager Dave Zanetell presented the families of Mike
O’Callaghan and Pat Tillman with commemorative plaques that included scaled-down
versions of the memorial pieces mounted on the new Bridge.
High
Resolution JPG
|
Attendees of the Dedication of the Mike O’Callaghan-Pat Tillman Memorial Bridge
arrived via Regional Transportation Commission of Southern Nevada double-decker
buses.
High
Resolution JPG
|

Guests of Bridging America enjoying the memorial wall in the pedestrian plaza,
just north of the new Mike O’Callaghan-Pat Tillman Memorial Bridge.
High
Resolution JPG
|
Families walking the entire length of the new Mike O’Callaghan-Pat Tillman
Memorial Bridge at Bridging America.
High
Resolution JPG
|

Visitors enjoyed reading about the project on large panels in the pedestrian
plaza just north of the new Mike O’Callaghan-Pat Tillman Memorial Bridge.
High
Resolution JPG
|
The grand view of Bridging America on the new Mike O’Callaghan-Pat Tillman
Memorial Bridge.
High
Resolution JPG
|

A majestic view of the public celebration event Bridging America.
High
Resolution JPG
|
The U.S., Arizona and Nevada flags unfurl on a clear day at Bridging America.
High
Resolution JPG
|

At Bridging America, guests enjoyed the pedestrian walkway on the new Mike
O’Callaghan-Pat Tillman Memorial Bridge.
High
Resolution JPG
|
Commemorative, metallic blue bottled water kept the crowd well hydrated at
Bridging America.
High
Resolution JPG
|

Souvenirs of this shot of the new Mike O’Callaghan-Pat Tillman Memorial Bridge
and the Hoover Dam as the backdrop were given to all attendees at Bridging
America.
High
Resolution JPG
|
The Hualapai Tribe’s White Water Group performed a special song and Bird Dance
at the Dedication of the Mike O’Callaghan-Pat Tillman Memorial Bridge.
High
Resolution JPG
|
Video
|
Watch a time lapse video of the bridge being
constructed...
|
Colorado River Bridge Construction (27 MB) |
Images from October 2010 |
Colorado River Bridge...
|
High Resolution TIF (14 MB) |

High Resolution TIF (14 MB) |
High Resolution TIF (14 MB) |

High Resolution TIF (14 MB) |
High Resolution TIF (14 MB) |

High Resolution TIF (14 MB) |

High Resolution TIF (14 MB) |

High Resolution TIF (14 MB) |
High Resolution TIF (14 MB) |

High Resolution TIF (14 MB) |
High Resolution TIF (14 MB) |

High Resolution TIF (14 MB) |
High Resolution TIF (14 MB) |

High Resolution TIF (14 MB) |

High Resolution TIF (14 MB) |

High Resolution TIF (14 MB) |
High Resolution TIF (14 MB) |

High Resolution TIF (14 MB) |
Return to the Top |
Images from September 2010 |
Colorado River Bridge...
|
High Resolution TIF (14 MB) |

High Resolution TIF (14 MB) |

High Resolution TIF (14 MB) |

High Resolution TIF (14 MB) |

High Resolution TIF (14 MB) |

High Resolution TIF (14 MB) |

High Resolution TIF (14 MB) |

High Resolution TIF (14 MB) |
High Resolution TIF (14 MB) |

High Resolution TIF (14 MB)
|

High Resolution TIF (14 MB) |

High Resolution TIF (14 MB)
|

High Resolution TIF (14 MB)
|
Return to the Top |
Images from August 2010 |
Colorado River Bridge...
|

High Resolution TIF (14 MB) |

High Resolution TIF (14 MB)
|

High Resolution TIF (14 MB) |

High Resolution TIF (14 MB)
|

High Resolution TIF (14 MB)
|

High Resolution TIF (14 MB)
|

High Resolution TIF (14 MB)
|

High Resolution TIF (14 MB)
|

High Resolution TIF (14 MB)
|

High Resolution TIF (14 MB)
|

High Resolution TIF (14 MB)
|

High Resolution TIF (14 MB)
|

High Resolution TIF (14 MB)
|

High Resolution TIF (14 MB)
|
Return to the Top |
|
Images from June & July 2010
|
Colorado River Bridge...
|

High Resolution TIF (14 MB) |

High Resolution TIF (14 MB)
|
High Resolution TIF (14 MB) |

.
High Resolution TIF (14 MB)
|

High Resolution TIF (14 MB)
|

High Resolution TIF (14 MB)
|

High Resolution TIF (14 MB)
|

High Resolution TIF (14 MB)
|
Return to the Top |
Images from May 2010 |
Colorado River Bridge...
|

.
High Resolution TIF (14 MB) |

.
High Resolution TIF (14 MB)
|

.
High Resolution TIF (14 MB) |

.
High Resolution TIF (14 MB)
|

High Resolution TIF (14 MB)
|
Return to the Top |
Images from April 2010 |
Colorado River Bridge...
|

.
High Resolution TIF (14 MB) |

.
High Resolution TIF (14 MB)
|

.
High Resolution TIF (14 MB) |

.
High Resolution TIF (14 MB)
|

High Resolution TIF (14 MB)
|
Return to the Top |
Images from March 2010 |
Colorado River Bridge...
|

looking southeast
View of the bridge as seen from Nevada towards Arizona.
In the background, the Arizona approach roadway is visible.
High Resolution TIF (14 MB) |

looking south
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) and
the new US93 alignment as seen from above Hoover Dam.
The Arch is complete with all spandrel piers constructed. Steel girders remain
to be placed for spans 6 and 7 and portion of span 14. Stay-in-place steel
decking is erected between the girders at spans 10 and 11. Climbing scaffolding
is attached to pier 6-RT column.
High Resolution TIF (14 MB)
|

looking east
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge).
Left side of the picture – Steel girders are staged on the approach deck,
waiting to be set between the Arch spandrel piers. Stay-in-place steel decking
is erected between the girders at spans 10 and 11.
Right side of the picture – A mobile crane is set on the deck, servicing workers
below at the AZ skewback footing.
High Resolution TIF (14 MB) |

looking north
View of the bridge as seen from Nevada towards Arizona.
Steel girders are staged on the Nevada approach deck, waiting to be set between
the Arch spandrel piers. Stay-in-place steel decking is erected between the
girders at spans 10 and 11.
In the background, the Arizona approach roadway is visible.
High Resolution TIF (14 MB)
|

High Resolution TIF (14 MB)
|
Return to the Top |
Images from February 2010 |
Colorado River Bridge...
|

.
High Resolution TIF (14 MB) |

.
High Resolution TIF (14 MB)
|

.
High Resolution TIF (14 MB) |

.
High Resolution TIF (14 MB)
|

.
High Resolution TIF (14 MB) |

.
High Resolution TIF (14 MB)
|

.
High Resolution TIF (14 MB)
|
Return to the Top |
Images from January 2010 |
Colorado River Bridge...
|

looking east
A truck transports a 115’ long steel girder onto the NV approach and waits for
off loading. Attached to the top flanges of the girder, above the end plate, are
temporary support brackets the will suspend the girder in-place from the top of
the pier cap until PT bars are installed through the holes in the end plate and
attach the girder to the pier cap face.
High Resolution TIF (14 MB) |

looking west
In the Obayashi / PSM, JV precast yard located near Boulder City, workers
utilize a rubber tire gantry crane to hoist a 115’ long steel girder onto a
truck for transport to the bridge site.
High Resolution TIF (14 MB)
|

looking east
The North highline hoists and transports a steel girder out onto the Arch for
placement between Pier 10 and 11 spandrel column pier caps. On the NV approach
deck, several girders are stage for sequenced placement. The South highline is
in use, delivering materials to waiting crews on the Arch. To the bottom left of
the picture, the orange stripping platform is cantilevered over the completed
right barrier railing to allow worker access to the underside of the deck.
Across the canyon, a Grove RT635C Crane sets on the AZ approach deck, above Pier
14, servicing crews working below on the AZ skewback.
High Resolution TIF (14 MB) |

looking northeast
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) from
downstream of the Hoover Dam.
On the Nevada approach, piers 3, 4, and 5 are visible. On the Arch, all spandrel
piers are completed with climbing scaffolding attached to piers 6-LT\RT and
13-LT columns. Pier 13-RT column has system scaffolding encasing it for worker
access.
The north highline crane transports a steel girder out for erection between Pier
10 and 11 spandrel column pier caps. The South highline is returning after
delivering crews to work areas on the Arch.
High Resolution TIF (14 MB)
|

looking north
Parked partially on the bridge deck at span 1, Olsen Beal crews attach highline
crane rigging and prepare a steel girder for off loading. Safety lines have been
installed to the tops of the web flanges. Temporary support brackets will be
attached to web flanges above the end plates prior to setting this girder into
its final position between two spandrel column pier caps.
High Resolution TIF (14 MB) |

looking southeast
As seen from the existing US93 Hairpin in Nevada, the completed Arch spans
across the Colorado River.
From right to left side of the picture – Spandrel Pier 6 is visible with
climbing scaffolding attached to the left & right columns. Piers 7 through 13
are completed with pier caps in place. Steel girders spanning between pier 9 and
10 (span 10) and between 10 and 11 (span11) are erected with access scaffolding
visible, suspended from the pier caps.
Spanning the canyon above the bridge are the twin cables of the highline crane
systems.
High Resolution TIF (14 MB)
|
Return to the Top |
Images from December 2009 |
Colorado River Bridge...
|

looking south
View of two of four steel girders, set in place, spanning between piers 9 and
10. Suspended from the top of the piers caps, are temporary platforms to allow
worker access for steel girder placement.
Utilizing the cantilevered man basket, suspended from the south highline,
Obayashi / PSM, JV crews access the underside of the right Arch rib below pier
10 to perform finishing work of the Arch soffit.
High Resolution TIF (14 MB) |

looking north
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) from
downstream of the Hoover Dam.
On the Nevada approach, piers 3, 4, and 5 are visible. On the Arch, Spandrel
Piers 6 through 13 are completed with their caps spanning between the left and
right columns. Two of four steel girders span between piers 9 and 10. Utilizing
the cantilevered man basket, suspended from the south highline, Obayashi / PSM,
JV crews access the underside of the right Arch rib to perform finishing work.
High Resolution TIF (14 MB)
|

looking southeast
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge)
progress as seen from existing US93 hairpin in Nevada.
Left to Right side of the picture – The completed Arizona
approach with the deck constructed to Pier 14. Climbing scaffolding is attached
to Pier 13-LT. Obayashi / PSM, JV crews remove system scaffolding from Pier
13-RT. Completed pier caps are visible for piers 13, 12, 11, 10, and 9 with
temporary access platforms attached. Moveable access platforms ride the top of
the Arch between piers 11 and 12 for finishing operations. Below the right arch
rib, a cantilevered man basket is suspended from the south highline to allow
finishing operations of the Arch soffit.
High Resolution TIF (14 MB) |

looking northwest
On the Nevada approach deck, steel girders are staged with steel safety lines
attached along the top of the upper flange. These girders, weighing upwards of
50 tons will be transported by the highline crane and placed to span between the
spandrel pier caps, on top of which, the concrete roadway deck will be
constructed.
High Resolution TIF (14 MB) |

looking south
On the Nevada approach deck, Obayashi / PSM, JV crews place concrete to
construct the southbound right side barrier railing.
High Resolution TIF (14 MB) |

looking east
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge)
progress as seen from the right of Abutment 1 in Nevada.
Left side of the picture – The completed Nevada approach with the deck
constructed to Pier 5. Obayashi / PSM, JV crews continue constructing the
southbound right side barrier railing. Steel girders are staged on the deck,
awaiting placement between spandrel piers.
Right side of the picture – all spandrel piers and pier caps are
completed. Scaffolding encases piers 6, 7, and 13. Temporary platforms are
suspended from the tops of the piers caps to allow worker access for steel
girder placement.
High Resolution TIF (14 MB) |
Return to the Top |
Images from November 2009 |
Colorado River Bridge...
|

looking north
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) from
downstream of the Hoover Dam.
On the Nevada approach, piers 2, 3, 4, and 5 are visible. On the Arch, Pier 6 is
erected to segment 13, Piers 7, 8, 9, 10, 11 and 12 are completed with the
falsework for their pier caps spanning between the left and right columns, and
Pier 13 is completed with the climbing scaffolding attached at the bottom of the
left column.
High Resolution TIF (14 MB) |

looking east
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge)
progress as seen from the right of Abutment 1 in Nevada.
Left side of the picture – The completed Nevada approach with the deck
constructed to Pier 5. Obayashi / PSM, JV crews construct formwork for the
southbound right side barrier railing.
Right side of the picture – all spandrel piers are completed with the
exception of Pier 6. Falsework and formwork for Piers 7 and 12 spans between
their left and right columns. Caps at Piers 8, 9, 10, and 11 are completed and
formwork removed.
High Resolution TIF (14 MB) |

looking southeast
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) as
seen from the deck at Pier 5.
Spandrel Pier 6-right is erected to segment 18, Pier 6-left to segment 16.
Utilizing the highline, Olsen Beal crews are transported off of Pier 6-left in a
man basket. Pier 6-right is completed with its 18th segment set. Further out on
the Arch, Pier 7 is completed with the falsework and formwork for the pier cap
in place. Spanning between the left and right ribs of the Arch at each pier,
precast concrete panels encase the steel strut members.
High Resolution TIF (14 MB) |

looking southwest
As seen from the existing US93 Hairpin in Nevada, the completed Arch spans
across the Colorado River.
From right to left side of the picture – Spandrel Pier 6-right is erected to
segment 18, Pier 6-left to segment 16. Pier 7 is completed with the falsework
and formwork for the pier cap in place. Caps at Piers 8, 9, 10 and 11 are
completed with their formwork stripped. Falsework and formwork for Pier 12’s cap
is set.
Spanning the canyon above the bridge are the twin cables of the highline crane
system.
High Resolution TIF (14 MB) |

looking northwest
On the Nevada approach, Obayashi / PSM, JV crews set formwork for the southbound
right side barrier railing. A Quality Control field engineer inspects the
operation.
High Resolution TIF (14 MB) |

looking west
Underside view of the bridge as seen from the existing US93 at the Nevada
Hairpin. Utilizing an under slung mobile scaffolding, Obayashi / PSM, JV crews
remove deck overhang brackets from spans 1 and 2. High above the deck, the
highline cranes transport materials out to the Arch.
High Resolution TIF (14 MB) |

looking south
The Arizona Approach as viewed from the Hoover Dam parking lot in Arizona.
From left to right side of the picture – the completed deck and Pier 14.
Pier 13 is completed, awaiting placement of pier cap falsework. Piers 12 and 11
are completed with formwork and falsework in place for the caps. Scaffolding
encases the columns of Piers 11, 12, and 13-left for worker access. At the far
right, the cap of Pier 10 is visible above the Arch. A temporary access bridge
spans between the skewback footing of Pier 14 and the Arch at Pier 13.
High Resolution TIF (14 MB) |
Return to the Top |
Images from October 2009 |
Colorado River Bridge...
|

looking southwest
On the Arizona approach, Olsen Beal crews remove the temporary pylons from above
Pier 14 using a Liebherr LTM1400-7.1 crane.
Right Center of the picture – Utilizing the highline crane, Olsen Beal
crews erect segment 5 of Pier 11-left.
High Resolution TIF (14 MB) |

looking north
On the Nevada approach, Obayashi / PSM, JV crews assemble pier cap falsework and
formwork.
High Resolution TIF (14 MB) |

looking south
On the Nevada approach, a delivered precast spandrel column segment waits to be
transported out onto the Arch by the highline crane system. Crews attach
temporary platforms to the sides of the segments for worker access. Steel post
tensioning rods are pre-loaded into the vertical ducts in the segment walls
along with a survey prism, attached to the upper portion of this segment prior
to transportation.
High Resolution TIF (14 MB) |

looking east
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) from
the right side of abutment 1.
Left side of the picture – The completed Nevada approach, with piers 4
and 5 visible.
Center to Right side of the picture – Pier 7 is erected to segment 3.
Piers 8, 9, 10, and 11 are complete and have cap falsework in place. Between the
two Arch ribs, the steel struts are encased in pre-cast concrete panels.
High Resolution TIF (14 MB) |

looking northeast
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) from
downstream of the Hoover Dam.
On the Nevada approach, piers 3, 4, and 5 are visible. On the Arch, spandrel
columns are completed at Piers 8, 9, 10, and 11 with the falsework for their
pier caps spanning between the left and right columns. Pier 7 is erected to
segment 4, Pier 12-left to segment 7 and Pier 12-right to segment 10.
High Resolution TIF (14 MB) |

looking south
Left side of the picture – Utilizing the highline crane, Olsen Beal crews erect
segment 2 of Pier 13-right. Pier 13-left has segment 1 erected on top of the
plinth. To the left of Pier 13, an access bridge spans between the Arch and Pier
14
Right side of the picture – Pier 12-right is erected to segment 9 while
Pier12-left to segment 7.
High Resolution TIF (14 MB) |

looking southwest
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) as
seen from Arizona, looking towards Nevada.
Left side of the picture – The pier cap falsework is erected on top of
Piers 8, 9, and 10. Olsen Beal crews continue erecting precast concrete spandrel
pier column segments at Pier 7.
Right Center of the picture – the completed Nevada approach is visible.
High Resolution TIF (14 MB) |

looking west
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) from
above the left side of abutment 2, facing Nevada.
Left side of the picture – The completed Arizona approach and Pier 14.
Center to Right side of the picture – The completed Arch with spandrel
columns in various stages of completion. Pier 13-left has segment 1 erected,
Pier 12-right is erected to segment 10, Pier 12-left to segment 7, Pier 11 is
complete with the cap falsework spanning between the columns. Behind Pier 11,
completed Piers 10, 9, and 8 are visible. The steel struts between the two Arch
ribs are encased in pre-cast concrete panels.
High Resolution TIF (14 MB) |

looking southeast
As seen from the existing US93 Hairpin in Nevada, the completed Arch spans the
Colorado River.
Formwork for Pier 6 plinths are in place. Pier 7 is erected to segment 3; Piers
8, 9, 10, and 11 are complete and have cap falsework in place. Between the two
Arch ribs, pre-cast concrete panels encase the steel struts.
High Resolution TIF (14 MB) |

looking northeast
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) from
the right side of abutment 1.
Right Center of the picture – The Arch is complete. An Arch strut is
erected between the ribs at Pier 6 and precast concrete spandrel pier column
segments at erected at Pier 7.
Left Center of the picture – On the Nevada approach, pier cap falsework
is being constructed.
High Resolution TIF (14 MB) |

looking west
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) from
above the left side of abutment 2, facing Nevada.
On the Arch, Olsen Beal crews are erecting precast concrete spandrel pier
segments at Piers 7, 8, 9, 10, 11, and 12. Temporary platforms are attached to
the sides of the segments for worker access.
On the Nevada approach, pier cap falsework is being constructed. Once finished,
they will be transported out and attached to, and span between, the completed
pier columns.
High Resolution TIF (14 MB) |
Return to the Top |
Images from September 2009 |
Colorado River Bridge...
|

looking southwest
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) from
Hoover Dam.
The Arch is completed with a majority of the temporary forestays and backstays
removed. The temporary pylons for the cable stays remain standing on top of Pier
5 (Nevada) and 14 (Arizona). Utilizing the highline crane, Obayashi / PSM, JV
crews remove work platforms from on top of Arizona pylons.
High Resolution TIF (14 MB) |

looking west
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) from
the left side of abutment 2, facing Nevada.
The Arch is completed with a majority of the temporary stays removed. Obayashi /
PSM, JV crews are installing the precast concrete panels around the Arch strut
at Pier 11. Formwork is set for construction of the spandrel column plinths at
Piers 10, 11, 12, and 13.
High Resolution TIF (14 MB) |

looking east
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) from
the right side of abutment 1 with a majority of the temporary stays removed.
Obayashi / PSM, JV crews are in the process of removing the remaining stays and
temporary pylons. On the Arch, work is progressing to construct the plinths for
the spandrel columns and installation of the precast concrete panels around the
Arch struts.
High Resolution TIF (14 MB) |

looking southeast
Obayashi / PSM, JV crews removing the stay cables from the temporary pylons on
the Nevada approach, above Pier 5.
High Resolution TIF (14 MB) |

looking southeast
Obayashi / PSM, JV crews removing the stay cables from the temporary pylons on
the Nevada approach, above Pier 5.
High Resolution TIF (14 MB) |

looking east
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman
Memorial Bridge) from the right side of abutment 1.
Left side of the picture –
Olsen Beal crews continue removal of the temporary pylons from above Pier 5
using a Liebherr LTM1400-7.1 crane.
Right Center of the picture –
the completed Arch with precast spandrel column segments erected at Piers
8-LT\RT, 9-LT, 10-LT, and 11-LT\RT. Crews are at Pier 10-RT waiting for
the highline to deliver its first segment.
High Resolution TIF (14 MB) |

looking north
Using a crawler crane, Olsen Beal crews unload a precast Spandrel column segment
and prepare it for transport to Pier 10 by the highline crane. The segment has
work scaffolding attached to the exterior sides and vertical post tensioning
bars inserted into the ducts.
High Resolution TIF (14 MB) |

looking east
Left side of the picture – on the Nevada approach, above Pier 5, Olsen Beal
crews continue removal of the temporary pylons using a Liebherr LTM1400-7.1
crane.
Center of the picture – the south highline crane carries a precast Spandrel
column segment out for erection at Pier 10.
High Resolution TIF (14 MB) |
Return to the Top |
Images from August 2009 |

View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) as
seen from along side of Abutment 2 in Arizona.
The Nevada and Arizona Arch cantilevers are constructed to segment 26 with the
closure segment remaining to be constructed. The temporary stay system is
complete with all the forestay/backstays installed.
Spanning between the two ribs of the Arch are the Arch struts (grey steel X
structures), connecting the ribs together.
At the right side of the picture, the Nevada approach is visible.
Spanning the canyon, above the temporary pylon is the highline crane system.
High
Resolution TIF (14 MB) |

Left side of the picture – The Arizona Arch headings are constructed
out to segment 26 with all the forestays installed. Spanning between the two
ribs is a temporary strut which will be kept in place until the permanent Arch
strut is erected at segment 24.
Right side of the picture - The Nevada Arch headings are constructed out to
segment 26 with all the forestays installed and the permanent Arch strut erected
at segments 19 & 24.
High
Resolution TIF (14 MB) |

View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) from
below. The Arch cantilevers are nearing connection with the closure segment
remaining to be constructed.
Left side of the picture – The Nevada Arch cantilevers are constructed out to
segment 26. Arch struts are erected between the ribs at segments 19 & 24.
Right side of the picture - The Arizona Arch headings are constructed out to
segment 26. An Arch strut is erected between the ribs at segments 19, with a
temporary strut at segment 23
High
Resolution TIF (14 MB) |

View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) from
Hoover Dam.
The Nevada and Arizona Arch cantilevers are constructed to segment 26 with the
closure segment remaining to be constructed.
The temporary pylons for the cable stays are constructed on top of Pier 5 in
Nevada with all the Forestay/backstays installed.
Arch struts (grey steel X structures), connecting the two Arch ribs, are
constructed at Nevada segments 7, 13, 19, and 24. On top of the Arch ribs, at
these locations, precast column segments for the spandrel piers will be erected.
High
Resolution TIF (14 MB) |

View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) from
downstream of the Hoover Dam.
Left side of the picture – The Nevada approach is visible with the Arch headings
projecting outward to segment 26 with all Stay systems installed.
Right side of the picture - The Arizona approach is visible with the Arch
headings projecting outward to segment 26 with all Stay systems installed.
High
Resolution TIF (14 MB) |

Left side of the picture – The Arizona Arch headings are constructed
out to segment 26 with all the forestays installed. Spanning between the two
ribs is a temporary strut which will be kept in place until the permanent Arch
strut is erected at segment 24.
Right side of the picture - The Nevada Arch headings are constructed out to
segment 26 with all the forestays installed and the permanent Arch strut erected
at segment 24.
Obayashi / PSM, JV crews are currently constructing formwork for the closure
segment to complete the connection between the Nevada and Arizona cantilevers.
High
Resolution TIF (14 MB) |

View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) from
downstream of the Hoover Dam.
Both ribs of the Arch are constructed to segment 26 with the form travelers
removed. Stay system installation is completed. At the center of the Arch, light
can be seen coming from the interior of the Arch ribs, shining through the gap
between the Nevada and Arizona cantilevers.
High Resolution TIF (14 MB) |
Return to the Top |
Images from June 2009 |
Colorado River Bridge...
|

looking southwest
View of the Arizona approach of the CO River Bridge (Mike O'Callaghan-Pat
Tillman Memorial Bridge).
The temporary pylons for the cable stays are constructed on top of Pier 14. The
Arch projects outward to segment 22 with forestay cables spanning between the
pylons and the Arch. Backstays span between the temporary pylon and the backstay
anchor block.
Arch struts (grey steel X structures), connecting the two Arch ribs, are
constructed at Arizona segments 7, 13, and 19. On top of the Arch ribs, at these
locations, precast column segments for the spandrel piers will be erected.
Forestays 11 are installed into the temporary pylon heads, waiting installation
into the Arch ribs at segments 22. Backstays F are fabricated on the Arizona
approach and await installation.
High Resolution TIF (14 MB) |

looking northeast
View of the Nevada approach of the CO River Bridge (Mike O'Callaghan-Pat Tillman
Memorial Bridge).
The temporary pylons for the cable stays are constructed on top of Pier 5. The
Arch projects outward to segment 22 with forestay cables spanning between the
pylons and the Arch. Backstays span between the temporary pylon and the backstay
anchor block.
Arch struts (grey steel X structures), connecting the two Arch ribs, are
constructed at Nevada segments 7, 13, and 19. On top of the Arch ribs, at these
locations, precast column segments for the spandrel piers will be erected.
High Resolution TIF (14 MB) |

looking southwest
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) as
seen from above Hoover Dam.
Left side of the picture – The Arizona approach is visible with the
Arch headings projecting outward to segment 23.
Right side of the picture - The Nevada approach is visible with the Arch
headings projecting outward to segment 22.
High Resolution TIF (14 MB) |

looking northeast
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) from
downstream of the Hoover Dam.
Left side of the picture – In Nevada, both ribs of the Arch are
constructed to segment 22. The form travelers are launched out to segment 23
with forestays installed to segment 20.
Right side of the picture - In Arizona, both ribs of the Arch are
constructed to segment 22. The left form traveler is launched out to segment 23
with forestays installed to segment 20.
High Resolution TIF (14 MB) |

looking northeast
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) with
Hoover Dam and Lake Mead in the background.
High Resolution TIF (14 MB) |

looking south
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge).
Left side of the picture – The Arizona approach alignment along with the Kingman
Wash interchange and the Sugar Loaf Mountain Bridge.
Right side of the picture - The construction office complex situated in the
future Pedestrian Plaza parking lot. The almost complete pedestrian access ramp
zigzags up the mountain side from the office area to the bridge abutment 1.
High Resolution TIF (14 MB) |

looking southwest
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) and
the new US93 alignment as seen from above Hoover Dam.
Lower Left to top right of the picture – The current US93 alignment
winds from Arizona, across Hoover Dam, and on into Nevada.
High Resolution TIF (14 MB) |
Return to the Top |
Images from May 2009 |
Colorado River Bridge...
|

looking southeast
In the foreground, an Obayashi / PSM, JV worker and QC engineer place imbeds and
adjust reinforcing steel in preparation for top slab exterior formwork to be set
on segment NV22-LT in Nevada.
In the background, the left and right Arch ribs project outward from the AZ
skewback footing.
High Resolution TIF (14 MB) |

looking southeast
View of the left / right Arch ribs as they project outward from the AZ skewback
footing. The outer form of the form traveler on the left rib is launched out to
segment 22 and is waiting for the reinforcing steel cage to be set. The form
traveler on the right rib is currently at segment 21 and crews are removing the
top slab exterior formwork and preparing for the collapsing of the inner core
formwork. The south highline crane is being rigged to the formwork preparing for
removal.
The forestays are visible, spanning from the temporary pylon above Pier 14 and
connecting to the Arch.
High Resolution TIF (14 MB) |

looking northeast
Arch segment NV19-LT diaphragm / arch strut post-tensioning blister formwork
prior to concrete placement as viewed from inside the Nevada right arch rib. To
the left and right, the temporary forestay blister can be seen as constructed
alongside the Arch interior wall. Below the blisters are blockouts in the floor
slab where the temporary strut will be attached to the underside of the Arch
with post tensioning bars.
High Resolution TIF (14 MB) |

looking north
Working within the confines of a temporary platform at the Pier 8 Arch strut and
outfitted with personal fall protection equipment, Obayashi / PSM, JV personnel
set blockouts for the transverse post-tensioning bars that will attach the
strut, connecting the left and right arch ribs.
On top of the Arch rib, to the right, a template that holds the vertical
post-tensioning bars where the pier 8 right column is to be erected can be seen.
Connected to the exterior of the Arch and wrapped in white Burlene, is the
concrete supply pipe, spanning between the stationary concrete pump at the NV
hairpin and the placing boom. Access to the strut is provided through the round
access hatch in the Arch wall.
High Resolution TIF (14 MB) |

looking northwest
Looking back station down the exterior of the right arch rib in Nevada at the
forestays as they project downward from the temporary pylons erected on top of
pier 5. In the foreground, a template holds the vertical post-tensioning bars
where the pier 8 south column is to be erected. To the right, Obayashi / PSM, JV
personnel, outfitted with personal fall protection equipment, work within the
confines of a temporary platform, stripping formwork and preparing for the arch
strut placement.
High Resolution TIF (14 MB) |

looking north
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) from
downstream of the Hoover Dam.
Left side of the picture – In Nevada, the right rib of the Arch is
constructed to segment 21 and the form traveler is launched out to segment 22 on
the left rib. Crews are currently installing forestays to segment 22 and
backstays to the backstay anchor block on the NV approach.
Right side of the picture – The Arch, constructed to segment 21, from
the AZ skewback. A temporary bridge spanning between Pier 14 and the Arch can
bee seen. This allows simplified construction worker access to the Arch from the
Arizona approach area.
High Resolution TIF (14 MB) |
Return to the Top |
Images from April 2009 |
Colorado River Bridge...
|

looking south
View of the Arch as seen from the existing US93 at the Nevada hairpin.
Left side of the picture – The right and left Arch ribs cantilever from
the AZ skewback out to segment 17. A temporary work platform spans between the
ribs at segment 13 to allow for installation of the steel strut.
Right side of the picture – The Arch cantilevers out to segment 19 in
NV. The temporary forestay cables support the Arch until Arch completion. Crews
are in the process of installing forestays into the Arch behind the form
traveler system. A stairway system is attached to the outside of the Arch for
access to the form travelers.
High Resolution TIF (14 MB) |

looking north
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) from
downstream of the Hoover Dam.
Left side of the picture – The Arch, constructed to segment 19 from the
NV skewback. Crews are in the process of installing forestays into the Arch
behind the form traveler system.
Right side of the picture – The Arch, constructed to segment 17, from
the AZ skewback.
At the leading edge of the Arch cantilevers, crews continue to advance the form
travelers and construct Arch segments.
High Resolution TIF (14 MB) |

looking east
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge)
progress as seen from the right of Abutment 1 in Nevada.
Left side of the picture – The completed Nevada approach with the
temporary pylons for the cable stays constructed on top of Pier 5. The Arch
projects outward to segment 19 with forestay cables spanning between the pylons
and the Arch.
Right side of the picture – The completed Arizona approach with the
temporary pylons for the cable stays constructed on top of Pier 14. The Arch
projects outward to segment 17 with forestay cables spanning between the pylons
and the Arch.
Spanning the canyon overhead are the twin cableway cranes.
High Resolution TIF (14 MB) |

looking west
At the south back stay anchor block in Arizona, an Obayashi / PSM, JV crew
utilize hydraulic post-tensioning jacks to simultaneously stress a set of back
stays. These stays span between the anchor block and the temporary pylon head
above Pier 14.
High Resolution TIF (14 MB) |

looking southwest
On top of the South temporary pylon above Pier 14 in Arizona, an Obayashi / PSM,
JV crew position hydraulic post-tensioning jacks in preparation of stressing of
a set of forestays connected to the Arch. These cables span between the
temporary pylon head above Pier 14 and the arch.
High Resolution TIF (14 MB) |
Return to the Top |
Images from March 2009 |
Colorado River Bridge...
|

looking southwest
Nevada Approach and Arch headings as viewed from the crest of Hoover Dam. The
left and right ribs of the Arch are constructed out to segment 16. Six sets of
forestay cables span from the Arch ribs to the temporary pylons heads and Six
sets of backstays span between the head and the backstay anchor block.
Between the Arch ribs are the steel Strut assemblies, located where spandrel
Piers columns 6 and 7 will be erected.
High Resolution TIF (14 MB) |

looking southeast
As seen from the existing US93 Hairpin in Nevada, the left and right Arch ribs
project outwards over the Colorado River. Forestay cables span from the Arch
ribs to the temporary pylons above.
The Arch strut, connecting the two Arch ribs, is constructed at segment 7. On
top of the Arch ribs, at this location, precast column segments for Pier 6 will
be erected.
Attached to the top of the Arch ribs are temporary stairs, work platforms, and
cross rib access walkways. Workers climb these stairs daily on their way to the
form travelers.
High Resolution TIF (14 MB) |

looking east
View of the Nevada left from traveler, as seen from the right traveler.
High Resolution TIF (14 MB) |

looking northwest
Looking up from the Nevada Arch rib towards the temporary pylons above.
Forestays span between the pylon heads and the Arch ribs, sheathed in white HDPE
casing. To the left of the left pylon, a set of scaffolding stairs are attached
to allow personnel access to the pylon heads. These 155’ tall pylons will remain
in place with the stays attached to support the Arch until the Arch is
completed. After completion, all forestays, back stays, and pylons will be
removed.
High Resolution TIF (14 MB) |

looking north
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman
Memorial Bridge) from downstream of the Hoover Dam.
Left side of the picture
- The Arch, constructed to segment 16 from
the NV skewback. Forestay cables span from the Arch ribs to the temporary pylons
above Pier 5 and backstays span between the temporary pylons and the backstay
anchor block.
Right side of the picture
-
The Arch, constructed to segment 15, from the AZ skewback. Forestay cables span
from the Arch ribs to the temporary pylons above Pier 14 and backstays span
between the head and the backstay anchor block.
High Resolution TIF (14 MB) |

looking north
Aerial view of the Mike O'Callaghan-Pat Tillman Memorial
Bridge looking to the north from above the Arizona side of the canyon. The
Arch is approximately 55% complete.
Left side of the picture
– The Nevada approach is visible with the Arch headings projecting outward from
the canyon wall. The Arch is constructed to segment 15. Forestay cables
span from the Arch ribs to the temporary pylons above Pier 5 and backstays span
between the temporary pylon and the backstay anchor block.
Right side of the picture
– The Arizona approach is visible with the Arch headings projecting outward to
segment 14. A set of backstay cables are attached to the pylon heads,
waiting tensioning as Arch construction progresses outward.
High Resolution TIF (14 MB) |

looking south
Aerial view of the Mike O'Callaghan-Pat Tillman Memorial
Bridge looking to the south from above the Arizona side of the canyon.
Left side of the picture
–
Backstay cables extend from the pylons to the backstay
anchor blocks. One set of backstays are attached to the pylon head,
waiting tensioning as Arch construction progresses outward. A set of
scaffolding stairs are attached to the South pylon to allow personnel access to
the pylon heads.
Right side of the picture
– The Arizona approach is visible with the left and right Arch ribs constructed
to segment 15. The form travelers are at segment 16 with the reinforcing
cages installed. Five sets of forestay cables extend from the temporary
pylons above Pier 14 and attach to the Arch ribs.
High Resolution TIF (14 MB) |
Return to the Top |
Images from February 2009 |
Colorado River Bridge...
|

looking south
View of the Obayashi / PSM, JV on-site concrete batch plant. From this plant,
all concrete for the project is currently being produced.
High Resolution TIF (14 MB) |

looking southeast
View of the Arch from the existing US93 Nevada at the hairpin. A concrete truck
delivers another load of concrete to the awaiting pump in Arizona
Foreground - From Nevada, the Arch, projects outward from Pier 5
skewback footing. The vertical post tensioning bars extend upwards from the Arch
rib where Pier 6 will be erected, on each side of the steel Arch strut that
connects the two ribs. The form travelers are at segment 13.
Background - The Arizona approach and Arch ribs are visible across the
canyon.
High Resolution TIF (14 MB) |

looking south
Obayashi / PSM, JV crews unload concrete into the re-mixer and concrete pump
located on the Arizona skewback footing at Pier 14. Concrete is delivered to the
pump by the cableway crane system via an 8cy concrete bucket. From the pump,
concrete is conveyed to the placing boom where it is directed into the formwork
of the Arch segment under construction.
High Resolution TIF (14 MB) |

looking southeast
Inside the form traveler system at Arch Segment NV13-LT, Obayashi / PSM, JV
crews placed concrete into the bottom slab formwork. The slick line from the end
of the placing boom is directing the flow of concrete through an open pour
window in the formwork. Other crew members consolidate the placed concrete while
carpenters follow behind and close the windows securely as placement advances.
High Resolution TIF (14 MB) |

looking south
Nevada Approach and Arch headings as viewed from the crest of Hoover Dam during
night time operations. The left and right ribs of the Arch are constructed out
to segment 13.
Four sets of forestay cables span from the Arch ribs to the temporary pylons
heads and the two sets of backstays span between the head and the backstay
anchor blocks. Additional forestays and backstays are installed to the pylon
heads, waiting tensioning as Arch construction progresses outward.
High Resolution TIF (14 MB) |

looking south
Arizona Approach as viewed from the crest of Hoover Dam during night time
operations. The left and right ribs of the Arch are constructed out to segment
12 with the form traveler advanced to segment 13 where construction crews place
concrete for segment 13-LT. The concrete placing boom reaches out from segment
11 and directs pumped concrete into the formwork. Concrete is delivered by an
8cy bucket from the bridge deck at Pier 14 to the awaiting concrete pump at the
skewback footing, where it is pumped up the North Arch rib in a pipe to the
placing boom.
Four sets of forestay cables span from the Arch ribs to the temporary pylons
heads and the two sets of backstays span between the head and the backstay
anchor blocks.
High Resolution TIF (14 MB) |

looking north
View of the Mike O'Callaghan-Pat Tillman Memorial Bridge as seen from downstream
of Hoover Dam. Presently the Arch is approximately 50% complete.
Left side of the picture - The Arch, constructed to segment 13, from the
NV skewback. Forestay cables span from the Arch ribs to the temporary pylons
above Pier 5 and backstays span between the head and the backstay anchor block.
Right side of the picture - The Arch, constructed to segment 12, from
the AZ skewback. Forestay cables span from the Arch ribs to the temporary pylons
above Pier 14 and backstays span between the head and the backstay anchor block.
High Resolution TIF (14 MB) |

looking north
On the Nevada Arch headings, Obayashi / PSM, JV crews launch the inner core of
the form traveler and position it in place for the next segment to be
constructed.
High Resolution TIF (14 MB) |

looking northwest
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) from
the deck of the bridge at Pier 14, looking towards Nevada.
Top Left side of the picture – The left and right Arch ribs project
outward from the Nevada skewback, currently constructed to segment 13.
Bottom of the picture – The left and right Arch ribs in Arizona are
visible, currently constructed to segment 13. Temporary stay cables, sheathed in
white HDPE casing, extend down to the Arch from the temporary pylons above Pier
14.
High Resolution TIF (14 MB) |
Return to the Top |
Images from January 2009 |
Colorado River Bridge...
|

looking west
Crews from Steel Engineers complete the relocation of the pre-assembled Arch
Segment NV13-RT reinforcing steel cage from the fabrication template on the
Arizona approach to a staging bed. This cage weighs approximately 25 tons.
High Resolution TIF (14 MB) |

looking northwest
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge)
progress as seen from the South side of Abutment 2 in Arizona.
Right side of the picture – The completed Arizona approach with the
temporary pylons for the cable stays constructed on top of Pier 14. The right
and left Arch ribs are constructed to segment 10 with the Arch strut installed
at segment 7.
Center of the picture – The completed Nevada approach with the temporary
pylons for the cable stays erected on top of Pier 5. The right and left Arch
ribs are constructed to segment 12 with the Arch strut installed at segment 7.
Left side of the picture – Obayashi / PSM, JV survey crew set up to
survey across the canyon to a rod man on the North Arch rib to make geometry
control adjustments to the form traveler.
High Resolution TIF (14 MB) |

looking northwest
At the top of the South temporary pylon in Arizona, Obayashi / PSM, JV crews
utilize a winch system to pull into place backstay AO.
Visible at the right of this picture, forestays 3, 4, and 5 are installed,
connecting to and supporting the right Arch rib.
High Resolution TIF (14 MB) |

looking southeast
Looking down at the backstay anchor blocks, from the top of the South temporary
pylon in Arizona, Obayashi / PSM, JV crews fabricate the next series of stay
cables in the tray laying on the roadway alignment.
At the top of the picture, the North and South backstay anchor blocks are seen
with stays DI and DO installed in each. Crews are preparing for the installation
of backstays AI and AO.
Visible near the top right of the picture, the inner core launching rail of the
right form traveler is being hoisted by the cableway crane for placement on the
form traveler at the leading edge of the right Arch rib.
High Resolution TIF (14 MB) |

looking southeast
Looking down on the Arch from the roadway deck above Pier 5 in Nevada, the right
and left Arch ribs project outward over the Colorado River below.
The left and right Arch ribs are constructed out to segment 12 with reinforcing
cages set for segments 12. Obayashi / PSM, JV carpenter crews prepare to launch
the inner core formwork of the form travelers and install top slab formwork.
The Arch strut, connecting the two Arch ribs, is constructed at segment 7. On
top of the Arch ribs, at this location, precast column segments for Pier 6 will
be erected. A temporary bridge allows worker’s access to the Arch from the
existing US93 near the Nevada hairpin area.
High Resolution TIF (14 MB) |

looking south
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) as seen from the crest of the Hoover Dam.
Piers 15 and 14 appear to the left in this picture, while Pier 5, 4, 3, 2, 1
appear to the right. Temporary pylons for the cable stays are constructed on top
of Piers 5 and 14 with forestay cables spanning from the Arch ribs to the
temporary pylons heads and backstays spanning between the heads and the backstay
anchor blocks.
The Arch is constructed to segment 10 in Arizona and to segment 12 in Nevada.
High Resolution TIF (14 MB) |
Return to the Top |
Images from December 2008 |
Colorado River Bridge...
|

looking east
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) from
the deck of the bridge at Pier 5, looking towards Arizona.
The right and left Arch ribs are constructed out to segment 10. The left rib has
the reinforcing steel cage set for segment 11. Visible at segment 7 is the steel
strut member that connects both ribs together. Temporary stay cables, sheathed
in white PVC casing, are attached to the arch ribs at segments 6, 8, and 10.
High Resolution TIF (14 MB) |

looking north
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) from
downstream of the Hoover Dam.
Left side of the picture - The Arch, constructed to segment 10, from the
NV skewback. Forestay cables span from the Arch ribs to the temporary pylons
above Pier 5 and backstays span between the head and the backstay anchor block.
Right side of the picture - The Arch, constructed to segment 10, from
the AZ skewback. Forestay cables span from the Arch ribs to the temporary pylons
above Pier 5 and backstays span between the head and the backstay anchor block.
High Resolution TIF (14 MB) |

looking southwest
Left side of the picture - The inner core of the Arizona South form
traveler system, weighing approximately 30 tons, is removed from the Arch and
carried by the South highline to the Arizona approach for form resurfacing.
Right side of the picture – The two temporary pylons above Pier 14 rise
155’ above the bridge deck. These towers are part of the cable stay erection
system that will support the arch ribs until closure.
High Resolution TIF (14 MB) |

looking northwest
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) from
the deck of the bridge at Pier 14, looking towards Nevada.
Top Left side of the picture – The left and right Arch ribs project
outward from the Nevada skewback.
Center Left side of the picture – The inner core of the Arizona South
form traveler system is being hoisted by the highline crane for resurfacing of
the form panels.
Bottom of the picture – The left and right Arch ribs in Arizona are
visible with both inner core forms removed. Temporary stay cables, sheathed in
white PVC casing, extend down to the Arch from the temporary pylons above Pier
14.
High Resolution TIF (14 MB) |

looking west
On the Arizona approach, Obayashi / PSM, JV carpenter crews resurface the inner
core of the form traveler.
High Resolution TIF (14 MB) |
Return to the Top |
Images from November 2008 |
Colorado River Bridge...
|

looking south
Inside the Nevada left Arch rib, an Obayashi / PSM, JV carpenter constructs
formwork for the diaphragm at Arch segment NV07-LT. The portal through the wall
of the Arch rib will allow access to the strut.
High Resolution TIF (14 MB) |

looking east
Inside the Nevada left Arch rib, an Obayashi / PSM, JV carpenter prepares to set
formwork for the diaphragm at Arch segment NV07-LT. Water will be pumped through
the grey tubing after concrete placement to cool the concrete during the curing
period. The white ducts encase the post tensioning bars that will extend upwards
through the exterior of the Arch rib, for the Pier 6 Left column.
High Resolution TIF (14 MB) |

looking south
Arizona Approach as viewed from the crest of Hoover Dam during night time
operations. The left and right ribs of the Arch are constructed out to segment 9
with the form traveler advanced to and preparing for construction of segment 10.
The first and second sets of forestay cables span from segments 6 and 8 to the
temporary pylons heads and the first set of backstays span between the head and
the backstay anchor block. Connecting the two ribs at segment 7 is a temporary
strut. This will remain in-place until the permanent strut is erected.
High Resolution TIF (14 MB) |

looking east
As seen from the existing US93 Hairpin in Nevada, the left and right Arch ribs
project outwards over the Colorado River. The form traveler systems are secured
to segments NV10 and cantilevers out to form segment NV11. Forestay cables span
from the Arch ribs to the temporary pylons above. The vertical post tensioning
bars extend upwards from the Arch rib where Pier 6 will be erected.
High Resolution TIF (14 MB) |

looking southwest
Nevada Approach and Arch headings as viewed from the crest of Hoover Dam during
night time operations. The left and right ribs of the Arch are constructed out
to segment 10. The first and second sets of forestay cables span from the Arch
ribs to the temporary pylons heads and the first set of backstays span between
the temporary pylon head and the backstay anchor block.
High Resolution TIF (14 MB) |

looking northwest
View of an Arch strut as pre-assembled on the Arizona Approach. This strut will
be transported by the cableway cranes where it will be erected between the Arch
ribs at segment NV07.
High Resolution TIF (14 MB) |

looking northeast
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) as
seen during night time operations from downstream of Hoover Dam.
Left side of the picture - The Arch, constructed to segment 10, from the
NV skewback. Forestay cables span from the Arch ribs to the temporary pylons
above Pier 5 and backstays span between the head and the backstay anchor block.
Right side of the picture - The Arch, constructed to segment 9, from the
AZ skewback. Forestay cables span from the Arch ribs to the temporary pylons
above Pier 5 and backstays span between the head and the backstay anchor block.
High Resolution TIF (14 MB) |

looking southwest
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) as
seen from the roof of the Hoover Dam operations building.
Piers 15 and 14 appear to the left in this picture, while Pier 5 and 4 appear to
the right. Temporary pylons for the cable stays are constructed on top of Piers
5 and 14. The Arch projects outward from the skewback footings at the base of
Piers 5 and 14 while the twin cableway cranes traverse the canyon above.
High Resolution TIF (14 MB) |
Return to the Top |
Images from October 2008 |
Colorado River Bridge...
|

looking southeast
Looking across the canyon from the bridge deck above Pier 5, the left and right
ribs of the Arizona Arch headings project outward from Pier 14 skewback footing.
Above the bridge deck, the temporary pylons for the cable stays rise 155’. The
pylon heads are accessed by climbing the scaffolding stairway, attached to the
right pylon.
High Resolution TIF (14 MB) |

looking south
Arizona Approach and Arch headings as viewed from the crest of Hoover Dam. The
left and right ribs of the Arch are constructed out to segment 8 with the form
traveler advanced to and preparing for construction of segment 9. The first set
of forestay cables span from the Arch to the temporary pylons heads and the
first set of backstays span between the head and the backstay anchor block. The
North cableway crane is lowering materials to the awaiting crews at the form
travelers.
High Resolution TIF (14 MB) |

looking south
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) as seen from the crest of the Hoover Dam.
Piers 15 and 14 appear to the left in this picture, while Pier 5, 4, 3, 2, 1
appear to the right. Temporary pylons for the cable stays are constructed on top
of Piers 5 and 14. The Arch projects outward from the skewback footings at the
base of Piers 5 and 14.
High Resolution TIF (14 MB)
|

looking southwest
Nevada Approach and Arch headings as viewed from the crest of Hoover Dam. The
left and right ribs of the Arch are constructed out to segment 9. The first and
second sets of forestay cables span from the Arch ribs to the temporary pylons
heads and the first set of backstays span between the head and the backstay
anchor block.
High Resolution TIF (14 MB) |

looking northwest
Looking across the canyon from the bridge deck above Pier 14, the left and right
ribs of the Nevada Arch project outward from Pier 5 skewback footing. Above the
deck, are the temporary pylons for the cable stays with two sets of stays set in
place for each Arch rib. Beyond the pylons, the towers of the cableway cranes
are luffted to the North and South to position the loads they are hoisting above
their respective work areas. At the top left of this picture, chains are
visible, hanging down from the South cableway crane hook.
High Resolution TIF (14 MB) |

looking down
Looking down on the Arch from the roadway deck above Pier 5 in Nevada, the right
and left Arch ribs project outward over the Colorado River below.
Left side of the picture – The left Arch rib is constructed out to segment 9
and awaits the advancement of the form traveler. A temporary bridge allows
worker’s access to the Arch from the existing US93 near the Nevada hairpin area.
Right side of the picture – The right Arch rib is constructed to segment 8 and
has the form traveler set for construction of segment 9. Obayashi / PSM, JV
carpenter crews prepare to install top slab formwork.
High Resolution TIF (14 MB) |

looking southeast
Inside the Nevada left Arch rib, Steel Engineer’s iron workers place reinforcing
steel to construct the diaphragm at Arch segment NV07-LT. Directly above this
diaphragm, on the exterior of the Arch rib, precast segments for Pier 6 Left
will be erected.
Visible through the reinforcing steel, daylight shines in from the leading face
of the form traveler.
High Resolution TIF (14 MB)
|

looking west
As seen from the leading edge of the Nevada left from traveler, the right
traveler is set for construction of Arch segment NV10-RT. Looking back down the
Arch, the curvature takes shape.
The right column of Pier 5 projects from the Nevada skewback footing. The fore
cable stays, wrapped in white PVC sheathing, can be seen extending from the
Arch, to the temporary pylons above Pier 5.
High Resolution TIF (14 MB) |
Return to the Top |
Images from September 2008 |
Colorado River Bridge...
|

looking northwest
Left side of the picture – From the bridge deck of the Arizona approach,
a pre-assembled reinforcing cage for Arch segment NV07-RT is hoisted by the
South Cableway Crane and carried across the canyon.
Right side of the picture – The temporary pylons for the cable stays are
constructed on top of Pier 14. The backstay cables have been installed in the
pylon head and await installation into the backstay anchor block.
High Resolution TIF (14 MB) |

looking southeast
Crews from Steel Engineers prepare to set the pre-assembled reinforcing cage for
Arch segment NV07-RT into the form traveler formwork.
High Resolution TIF (14 MB)
|

looking northeast
A carpenter foreman from the Obayashi / PSM, JV stands atop the leading edge
formwork of Arch segment NV08-LT, conversing with crews working on the adjacent
segment NV07-RT.
High Resolution TIF (14 MB) |

looking east
Obayashi / PSM, JV’s crews install embedments into the top slab prior to
completion of formwork for Arch segment NV07-RT.
High Resolution TIF (14 MB)
|

looking southeast
As seen from the Pier 5 skewback footing in Nevada, the left and right Arch ribs
extend outwards towards Arizona with work continuing to cast segments NV07.
Across the canyon, columns of Pier 14 and the temporary pylons are visible.
High Resolution TIF (14 MB) |

looking down
Looking down on the Arch from the roadway deck above Pier 14
in Arizona, the right and left Arch ribs project outward over the Colorado River
below.
Left side of the picture
– The right Arch rib is constructed out to segment 6. Using the Cableway
Crane, iron workers place the pre-assembled reinforcing cage for segment 7.
Right side of the picture
– The left Arch rib is constructed to segment 6 and has the form traveler set
for construction of segment 7.
High Resolution TIF (14 MB)
|

looking southeast
Obayashi / PSM, JV’s crews constructing formwork for Arch segment NV07-LT.
Across the canyon, columns of Pier 14 temporary pylons, and the AZ Arch are
visible along with the Cableway Crane, lowering the pre-assembled reinforcing
cage for segment AZ-07 RT.
High Resolution TIF (14 MB) |

looking south
Lower right side of the picture – A pre-assembled reinforcing cage for Arch
segment AZ07-RT is hoisted by the South Cableway Crane and carried across the
canyon past the Arizona right form traveler.
Center of the picture – The temporary pylons for the cable stays rise 155’
above the Arizona approach bridge deck at Pier 14. Temporary cable stays are
installed from the Arch to the pylon head and will be used to support the Arch
until the closure segment is constructed. Near the bottom, the left and right
Arch ribs project outwards from the Pier 14 skewback footing, with the form
travelers set for Arch segments AZ07 left and right.
High Resolution TIF (14 MB)
|

looking northeast
Arizona Approach as viewed from down stream of Hoover Dam. The left and right
ribs of the Arch are constructed out to segment 6 with the form traveler
advanced to and preparing for construction of segment 7. The first set of
forestay cables span from segment 6 to the temporary pylons heads and the first
set of backstays span between the head and the backstay anchor block.
High Resolution TIF (14 MB) |
Return to the Top |
Images from August 2008 |
Colorado River Bridge...
|

looking south
View of the Arizona approach as seen from the crest of Hoover Dam.
The completed Arizona approach with the temporary pylons for the cable stays
constructed on top of Pier 14. At the base of Pier 14, the left Arch rib is
visible.
High Resolution TIF (14 MB)
|

looking southeast
View of the pre-assembled arch reinforcing steel cages stockpiled on the Arizona
approach.
High Resolution TIF (14 MB) |

looking down
Looking down on the Arch from the roadway deck above Pier 14 in Arizona, the
right and left Arch ribs project outward over the Colorado River below.
Left side of the picture – The right Arch rib is constructed out to segment 6
and awaits concrete placement.
Right side of the picture – The left Arch rib is constructed to segment 6 and
has the concrete placing boom extended to the right Arch rib in preparation of
concrete placement.
High Resolution TIF (14 MB)
|

looking north
Crews from Steel Engineers assembling arch reinforcing steel in a template on
the Arizona approach.
High Resolution TIF (14 MB) |

looking northwest
View of the temporary stay cable pylons constructed above Pier 14 in Arizona.
Crews are working on erecting the stairway scaffolding to allow access to the
pylon heads. Spanning overhead are the twin cableway crane systems.
High Resolution TIF (14 MB)
|

looking north
View of the Arch struts as stockpiled on the Arizona Approach. Once assembled,
the strut will span between the Arch ribs to maintain alignment.
High Resolution TIF (14 MB) |

looking south
As seen from the existing US93 Hairpin in Nevada, the left and right Arch ribs
project outwards over the Colorado River. The form traveler systems are secured
to segments NV06 and cantilevers out to form segment NV07. the form traveler on
the right rib of the Arch has it’s left external form panel removed for
maintenance.
High Resolution TIF (14 MB)
|

looking south
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) as seen from the crest of the Hoover Dam.
Piers 15 and 14 appear to the left in this picture, while Pier 5, 4, 3, 2, 1
appear to the right. Temporary pylons for the cable stays are constructed on top
of Piers 5 and 14. The Arch projects outward from the skewback footings at the
base of Piers 5 and 14.
High Resolution TIF (14 MB) |

looking east
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge)
progress as seen from the right of Abutment 1 in Nevada.
Left side of the picture – The completed Nevada approach with the temporary
pylons for the cable stays constructed on top of Pier 5. At the base of Pier 5,
the right Arch rib is visible.
Right side of the picture – The completed Arizona approach with the temporary
pylons for the cable stays constructed on top of Pier 14. At the base of Pier
14, the right and left Arch ribs are visible.
Spanning the canyon overhead are the twin cableway cranes.
High Resolution TIF (14 MB)
|

looking west
View of the constructed stay cables as they lay on the Nevada approach bridge
deck, waiting insertion into the Arch and temporary pylon head. These cables are
part of the cable stay erection system that will support the arch ribs until
closure.
High Resolution TIF (14 MB) |
Return to the Top |
Images from July 2008 |
Colorado River Bridge...
|

looking west
Obayashi / PSM, JV’s temporary concrete batch plant, located in the Boneyard
laydown area.
High Resolution TIF (14 MB)
|

looking northwest
View of the south temporary stay cable anchor and highline crane at the Abutment
1 area in Nevada. Utilizing steel beams, Obayashi / PSM crews construct trays
for fabrication of the stay cables between the tower bases.
The south temporary stay cable anchor is exposed and is waiting installation of
the stays. The south highline crane system is currently luffed to the north for
delivery of materials to the Arch.
High Resolution TIF (14 MB) |

looking down
Looking down on the Arch from the roadway deck above Pier 5 in Nevada, the right
and left Arch ribs project outward over the Colorado River below.
Left side of the picture – The left Arch rib is constructed out to segment 6
and awaits the advancement of the form traveler. A temporary bridge allows
worker’s access to the Arch from the existing US93 near the Nevada hairpin area.
Right side of the picture – The right Arch rib is constructed to segment 6 and
has the form traveler set for construction of segment 7.
High Resolution TIF (14 MB)
|

looking southeast
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge)
progress as seen from the right of Abutment 1 in Nevada.
Left side of the picture – The completed Nevada approach with the temporary
pylons for the cable stays constructed on top of Pier 5. At the base of Pier 5,
the right Arch rib is visible.
Right side of the picture – The completed Arizona approach with the temporary
pylons for the cable stays constructed on top of Pier 14. At the base of Pier
14, the right and left Arch ribs are visible.
Spanning the canyon overhead are the twin cableway cranes.
High Resolution TIF (14 MB) |

looking up
Utilizing the
cableway crane, Olsen Beal crews access the top of the
temporary stay pylons in Arizona to complete erection of the pylon head assembly.
High Resolution TIF (14 MB)
|

looking south
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge)
progress as seen from the existing US93 in Nevada.
The completed Arizona approach is visible with the right and left Arch ribs
cantilevered outward from the Arizona Skewback at the base of Pier 14.
High Resolution TIF (14 MB)
|

looking down
Looking down on the Arch from the roadway deck above Pier 14in Arizona,
the right and left Arch ribs project outward over the Colorado River below.
Left side of the picture
– The right Arch rib is constructed out to segment 4 and awaits final formwork
and concrete placement for segment 5.
Right side of the picture –
The left Arch rib is constructed to segment 5 and awaits final formwork and
concrete placement for segment 6. Below segment 5, a placing boom is
attached to the Arch in preparation of concrete placement.
High Resolution TIF (14 MB) |
Return to the Top |
Images from June 2008 |
Colorado River Bridge...
|

looking south
View of the Pier 5 columns as seen from the existing US93 Hairpin in Nevada.
Temporary scaffolding stairs allows access up the column to survey control
points. To the left of the base of the scaffolding, the Arch form traveler
system can be seen rising above the roadway elevation.
High Resolution TIF (14 MB)
|

looking south
As seen from the existing US93 Hairpin in Nevada, the left and right Arch ribs
project outwards over the CO River. The fully configured form traveler systems
are secured to segment NV05 and cantilevers out to form segment NV06.
High Resolution TIF (14 MB) |

looking southwest
Visible from the base of the Hoover Dam, the Arch begins to take shape.
Left side of the picture – Arizona approach spans from Abutment 2 to Pier 14.
The Arch projects outward from the Pier 14 skewback footing. Temporary pylons
for the cable stay erection system are partially completed on the bridge deck
above Pier 14.
Right side of the picture – The completed Nevada approach span from Pier 4 to
Pier 5, along with the left and right ribs of the Arch are visible. Above Pier
5, the temporary pylons for the cable stay erection system can be seen.
High Resolution TIF (14 MB)
|

looking southwest
View of the partially completed 155’ tall temporary pylon at Pier 14. These
towers are part of the cable stay erection system that will support the arch
ribs until closure.
High Resolution TIF (14 MB)
|

looking west
The north highline crane system delivers the 6th precast segment to waiting
Olsen Beal workers at the top of the temporary pylon on the right at Pier 14.
High Resolution TIF (14 MB) |
Return to the Top |
Images from May 2008 |
Interim Surfacing on the Arizona & Nevada Approaches...
|

looking west
View of the completed Nevada approach portion of the project between the Hoover
Dam BOR Warehouse Bridge and the Hoover Dam Canyon Bridge.
At the center of the picture, Las Vegas Paving personnel perform clean up work
near the Hoover Dam Lower Portal Road Bridge.
High Resolution TIF (14 MB)
|

looking east
View of the completed Nevada approach portion of the project between the Hoover
Dam Canyon Bridge and the Hoover Dam BOR Warehouse Bridge.
High Resolution TIF (14 MB)
|

looking west
View of the completed Nevada approach portion of the project near the Nevada
interchange as seen from the existing US93.
A Las Vegas Paving water truck readies to wash the roadway alignment in
preparation for final project acceptance.
High Resolution TIF (14 MB)
|

looking west
View of the completed Nevada approach portion of the project as seen from the
existing US93.
At the bottom left of the picture, the Hoover Dam Canyon Bridge is visible.
Near the top right of the picture, is the Nevada interchange, along with the
Goldstrike Canyon Road.
High Resolution TIF (14 MB)
|

looking southeast
View of the completed Arizona approach portion of the project as seen from the
Sugarloaf Mountain Bridge towards the Arizona Interchange.
High Resolution TIF (14 MB)
|
Return to the Top |
Colorado River Bridge...
|

looking northeast
Utilizing the highline crane system, Obayashi / PSM, JV workers hoist and
prepare to erect the first segment of the 155’ tall temporary pylon at Piers 5
as part of the cable stay erection system that will support the arch ribs until
closure.
High Resolution TIF (14 MB)
|

looking south
Obayashi / PSM, JV workers remove formwork and prepare to advance the form
traveler system from the recently constructed left arch rib segment NV05 out to
and reset for segment NV06.
Across the canyon, in Arizona, the left and right Arch ribs are visible
projecting from the skewback footing, nearly 1000’ away.
High Resolution TIF (14 MB)
|

looking south
View of the left and right Arch ribs as they project from the Pier 5 skewback
footing in Nevada.
Foreground – The left rib is currently constructed out to segment NV05.
Background – The right rib is currently constructed out to segment NV04.
Workers access the form system by the temporary stairs attached to the back of
the arch ribs. As the Arch is constructed, additional stairs will be added.
High Resolution TIF (14 MB)
|

looking west
View of the Nevada approach span of the Mike O'Callaghan-Pat Tillman Memorial
Bridge.
From left to right – The left and right ribs of the Arch project from the Pier
5 skewback footing. Piers 5 through 1 are completed along with the bridge deck
spanning between them.
At the far right, the two towers of the twin highline crane system can be seen.
High Resolution TIF (14 MB)
|

looking west
Obayashi / PSM, JV workers perform final checks of the Bidwell concrete
finishing machine prior to concrete placement for the deck of Arizona approach
from Pier 15 to Abutment 2.
Foreground – A side discharge conveyor system spans across the deck to assist
in concrete placement. The conveyor and the finishing system travels towards
Abutment 2 while placing the freshly placed concrete.
High Resolution TIF (14 MB)
|

looking southwest
View of the Mike O'Callaghan-Pat Tillman Memorial Bridge alignment looking from
Arizona towards Nevada.
Left side of the picture – Arizona approach spans from Abutment 2 to Pier 14.
Olsen Beal crews install steel stay-in-place decking between the girders prior
to deck reinforcement placement. Overhead, the highline crane system delivers
materials to the work area.
Right side of the picture – Across the canyon, the completed Nevada approach
span from Abutment 1 to Pier 5, along with the left and right ribs of the Arch
are visible.
High Resolution TIF (14 MB)
|

looking north
Preparing for concrete placement, Obayashi / PSM, JV workers assemble the
Bidwell concrete finishing machine on the Arizona approach.
High Resolution TIF (14 MB)
|
Return to the Top |
Images from April 2008 |
Interim Surfacing on the Arizona & Nevada Approaches...
|

looking north
View of the completed pavement on the Arizona approach portion of the project
looking towards the Sugar Loaf Mountain Bridge.
High Resolution TIF (14 MB)
|

looking southwest
Las Vegas Paving placing the first lift of asphalt pavement on the Nevada
approach portion of the project.
High Resolution TIF (14 MB)
|

looking west
Arizona Highways Safety Systems driving posts for the guard rail in Nevada.
High Resolution TIF (14 MB)
|

looking north
On the Arizona approach, Arizona Highways Safety Systems install guard rail
along the roadway alignment.
High Resolution TIF (14 MB)
|

looking south
Triple J Trenching constructing the slotted drain systems after the paving is
completed on the Arizona approach portion of the project.
High Resolution TIF (14 MB)
|
Return to the Top |
Colorado River Bridge...
|

looking north
View of the bridge alignment looking towards Hoover Dam as seen from downstream
of the dam.
Left side of the picture:
Completed Nevada approach span from Abutment 1 to Pier 5. At the bottom of Pier
5, the constructed Arch begins to project outward over the CO River.
Right side of the picture:
the Arizona approach span from Abutment 2 to Pier 14 near completion. At the
bottom of Pier 14, the formwork for the Arch segments are visible.
High Resolution TIF (14 MB)
|

looking northeast
Nevada approach from Abutment 1 to Pier 5.
At the center of the picture, Obayashi / PSM, JV workers prepare for concrete
placement for the bridge deck.
Near the top right, Olsen Beal crews install steel stay-in-place decking prior
to deck reinforcement placement.
High Resolution TIF (14 MB)
|

looking west
Obayashi / PSM, JV workers pre-assemble and attach access platforms to precast
temporary pylon towerheads.
High Resolution TIF (14 MB)
|

looking north
Ariel view of the Nevada approach from Abutment 1 to Pier 5. At the bottom of
Pier 5, the form traveler form system is cantilevered from the completed Arch as
it projects outward from the skewback.
High Resolution TIF (14 MB)
|

looking southeast
Ariel view of the Project alignment looking from Nevada towards Arizona.
In the foreground, the Nevada approach span of the Mike O'Callaghan-Pat Tillman
Memorial Bridge is nearing completion. Obayashi / PSM, JV workers prepare for
the final concrete pour to complete the bridge deck out to Pier 5.
In the background, the Arizona approach spans of the Mike O'Callaghan-Pat
Tillman Memorial Bridge are visible along with the roadway alignment leading up
to the bridge.
At the bottom center, the Pedestrian Plaza access ramp zigzags up the
mountainside from the future parking lot to allow access to the bridge’s
pedestrian walkway.
High Resolution TIF (14 MB)
|

looking south
View of the Arizona approach from Abutment 2 to Pier 14.
At the center of the picture, Olsen Beal crews install steel stay-in-place
decking between the girders prior to deck reinforcement placement.
At the left, the two towers of the twin highline crane system can be seen.
High Resolution TIF (14 MB)
|

looking north
Ariel view of the bridge alignment looking towards Hoover Dam.
High Resolution TIF (14 MB)
|
Return to the Top |
Images from March 2008 |
Interim Surfacing on the Arizona & Nevada Approaches...
|

looking south
Las Vegas Paving performing compaction of the asphalt pavement on the Arizona
approach portion of the project.
High Resolution TIF (14 MB)
|

looking south
Las Vegas Paving placing the first lift of asphalt pavement on the Arizona
approach portion of the project.
High Resolution TIF (14 MB)
|
Return to the Top |
Colorado River Bridge...
|

looking northwest
In Arizona, pre-assembled Arch reinforcing steel cages are stockpiled and await
placement as part of an Arch segment.
High Resolution TIF (14 MB)
|

looking west
View of underside of bridge spans 1 and 2 as seen from the existing US93 hairpin
in Nevada.
Working approximately 95’ above the ground, an Obayashi / PSM, JV worker
attaches the temporary orange overhang falsework brackets to the outside of the
steel girder of span 2.
High Resolution TIF (14 MB)
|

looking east
View of spans 3 and 4 as seen from the deck of the bridge.
In the foreground, Obayashi / PSM, JV workers survey grade and adjust the
overhang falsework brackets on the outside of the steel girder of span 2.
In the background, Olsen Beal
crews place stay in-place decking for bridge span 3,
between piers 3 and 4.
High Resolution TIF (14 MB)
|

looking southwest
Utilizing the south cableway crane system, Olsen Beal crews transport and place
steel stay in-place decking for bridge span 3, between piers 3 and 4. Hanging on
temporary supports between the girders, the bridge deck drain piping system can
be seen.
High Resolution TIF (14 MB)
|

looking southeast
View of the bridge alignment, looking from Nevada
towards Arizona.
In the foreground, crews from Steel Engineers place
reinforcing steel for the deck of span 1, between Abutment 1 and Pier 1.
In the background, Olsen Beal
crews place stay in-place decking for bridge span 3,
between piers 3 and 4.
High Resolution TIF (14 MB)
|

looking southeast
View of the bridge alignment from the existing US93 hairpin in Nevada looking
towards Arizona.
In the foreground, Obayashi / PSM, JV workers place concrete for Arch segment
NV04-Left
In the background, across the Colorado River, the Arizona Arch segments, along
with Pier 14 columns are visible, approximately 1100’ away.
High Resolution TIF (14 MB)
|

looking south
As seen from the existing US93 hairpin in Nevada, during a night shift
operation, a concrete pump truck delivers concrete to Obayashi / PSM, JV workers
for placement at Arch segment NV04-Left.
High Resolution TIF (14 MB)
|

looking northwest
View of a pre-assembled reinforcing steel cage being delivered to Arch segment
NV03-Right from the Abutment 2 area in Arizona. This 25’ long cage weighs
approximately 32,000 pounds and is delivered across the canyon with the south
cableway crane system.
Visible just below the cage is the trolley assembly of the north cableway crane
system.
High Resolution TIF (14 MB)
|
Return to the Top |
Images from February 2008 |
Interim Surfacing on the Arizona & Nevada Approaches...
|

looking southeast
View of the Arizona approach roadway prior to aggregate base placement. On ramp
B, near the Arizona interchange, Triple J Trenching is visible excavating and
installing conduits for future electrical crossings.
High Resolution TIF (14 MB)
|

looking west
Triple J Trenching crews place and compact backfill material for installation of
conduits for future electrical crossings on the Arizona approach.
High Resolution TIF (14 MB)
|

looking northwest
On the Nevada approach, Las Vegas Paving is hauling, placing, and compacting
aggregate base material onto the Nevada approach roadway alignment near the
Nevada interchange.
High Resolution TIF (14 MB)
|

looking west
View of a haul truck placing aggregate base material onto the Nevada approach
roadway alignment near the Hoover Dam Canyon Bridge.
High Resolution TIF (14 MB)
|

looking south
Las Vegas Paving shaping aggregate base material prior to compacting on the
Nevada approach roadway alignment.
High Resolution TIF (14 MB)
|
Return to the Top |
Colorado River Bridge...
|

looking east
The final span 2 steel girder is being transported from the abutment 1 area for
placement in span 2. This girder is approximately 100’ long and weighs 45 tons.
High Resolution TIF (14 MB)
|

looking north
Olsen Beal crews prepare cable rigging for hoisting and erecting steel girders
for the Nevada approach.
High Resolution TIF (14 MB)
|

looking west
Delivery of the steel girders for the Nevada approach.
High Resolution TIF (14 MB)
|

looking east
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge)
progress as seen from abutment 1 in Nevada.
Steel girders for span 1 are erected with 3 of the 4 placed for span 2.
Olsen Beal crews are transported in a man basket to pier cap 3 in preparation
for erection of the final girder for span 2.
High Resolution TIF (14 MB)
|

looking northwest
View of the Nevada approach columns with steel girders in span 2 erected along
with 2 of the 4 girders erected in span 3.
At the bottom of Pier 5, the completed Arch is visible cantilevered off of the
NV skewback footing.
High Resolution TIF (14 MB)
|

looking northwest
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge)
progress as seen from downstream of Hoover Dam.
At the left, the Nevada approach columns (Piers 1, 2, 3, 4, & 5) are visible
with steel girders in-place for spans 1, 2, and 3. Near the bottom of Pier 5,
newly constructed Arch segments cantilever off of the NV skewback footing.
To the right, the Arizona approach columns (Piers 14 & 15) can bee seen with the
girder placement completed. Below Pier 14, on the AZ skewback, formwork
cantilevers off of the footing.
High Resolution TIF (14 MB)
|
Return to the Top |
Images from January 2008 |
Colorado River Bridge...
|

looking southeast
Olsen Beal crews look on as the North highline crane hoists a 50 ton concrete
certification weight.
High Resolution TIF (14 MB)
|

looking southeast
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) as seen from abutment 1 in Nevada.
Center – The completed Pier 1 cap is awaiting steel girder placement.
System scaffolding encases the right column of Pier 1.
Above the pier cap, the North highline crane is being certified prior to use
with a 50 ton concrete block test load.
High Resolution TIF (14 MB)
|

looking southeast
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) as seen from abutment 1 in Nevada. Both operational highline cranes can
be seen in their fully constructed configuration.
Near the bottom of the photograph, piers caps for Piers 1, 2, 3, and 4 are
visible.
High Resolution TIF (14 MB)
|

looking northwest
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge)
progress as seen from downstream of Hoover Dam.
At the left, the Nevada approach columns (Piers 1, 2, 3, 4, & 5) are visible
awaiting steel girder placement.
To the right, the Arizona approach columns (Piers 14 & 15) can bee seen with the
girder placement nearing completion.
Spanning the canyon above the Approaches, the 3” track cables of the highline
cranes are visible.
High Resolution TIF (14 MB)
|

looking south
The 50 ton concrete block test load traverses the canyon via
the north highline crane.
At the left of the
photograph, the Arizona approach is visible.
High Resolution TIF (14 MB)
|

looking north
Crews from Steel Engineers assembling arch reinforcing steel in a template on
the Arizona approach.
High Resolution TIF (14 MB)
|

looking southwest
Obayashi / PSM, JV field engineer performs construction surveying from the
existing US93 near the Nevada hairpin area.
High Resolution TIF (14 MB)
|

looking northwest
View of the assembled precast temporary stay cable towerhead. These towerheads
will be constructed on top of a 130’ tall temporary tower at Piers 5 and 14 as
part of the cable stay erection system that will support the arches until
closure. At the completion of arch construction, they will be removed along with
the temporary stay cables.
High Resolution TIF (14 MB)
|
Return to the Top |
Images from December 2007 |
Colorado River Bridge...
|

looking southwest
View of the Nevada approach columns of the future CO River Bridge (Mike
O'Callaghan-Pat Tillman Memorial Bridge) as seen from the existing US93 in
Arizona.
From left to right:
In Arizona - Olsen Beal crews utilize a Manitowoc 2250 crane to assemble
the trolley and attach the slack carriers for the highline crane system
Piers 5, 4, 3, 2, 1 - columns are complete with their pier cap visible
above the cap falsework.
Abutment 1 – can be seen to the far right.
In Nevada - Olsen Beal crews utilize a Manitowoc M250 crane to perform
work on the Nevada side of the highline crane system.
High Resolution TIF (14 MB)
|

looking south
At the NV skewback footing, Obayashi / PSM, JV crews assemble the form traveler
to its full configuration onto the left Arch rib in preparation for construction
of the third segment.
To the right of this picture, an additional crew assembles formwork in
preparation for construction of right Arch rib segment two.
High Resolution TIF (14 MB)
|

looking southeast
High above the roadway alignment in Nevada, Olsen Beal crews continue
construction of the new highline crane systems.
High Resolution TIF (14 MB)
|

looking south
Utilizing a Manitowoc M250 crane located in the abutment 1 area in Nevada; Olsen
Beal crews attach the slack carriers onto the 3” cables of the South highline
crane system.
High Resolution TIF (14 MB)
|

looking northeast
In Arizona, steel girders make up a reinforcing steel fabrication jig. On the
exterior of this jig, iron workers will assemble Arch segment reinforcing steel
cages. Once complete, the cages will be lifted off of the end of this jig and
transported out to the form traveler and placed as part of an Arch segment.
High Resolution TIF (14 MB)
|

looking southwest
In Arizona, high above the roadway alignment at Abutment 2, Olsen Beal crews
construct the highline crane system by attaching the trolley and slack carriers
to the 3” cables that span the canyon.
Below Pier 14, on the AZ skewback, formwork cantilevers off of the footing in
preparation for an arch segment concrete placement.
High Resolution TIF (14 MB)
|

looking northeast
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) as seen from downstream of Hoover Dam.
At the left, the Nevada approach columns (Piers 1, 2, 3, 4, & 5) are visible
awaiting steel girder placement. Near the bottom of Pier 5, newly constructed
Arch segments cantilever off of the NV skewback footing.
To the right, the Arizona approach columns (Piers 14 & 15) can bee seen with the
girder placement completed.
The towers of the new highline crane system can bee seen to the edge of the
picture, along with their 3” cables spanning the canyon between them.
High Resolution TIF (14 MB)
|

looking southwest
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) as seen from upstream of Hoover Dam.
Piers 15 and 14 appear to the left in this picture, while Pier 5, 4, 3, 2, 1
appear to the right.
Steel girders are in-place for the approach spans in Arizona while crews
construct the new highline crane system.
High Resolution TIF (14 MB)
|
Return to the Top |
Images from November 2007 |
Colorado River Bridge...
|

looking north
In the contractor’s laydown yard, Obayashi / PSM, JV crews prepare formwork to
cast concrete panels for the exterior of the Arch strut steel frames. A
completed panel is hoisted by crane and transported to the staging area,
awaiting erection.
High Resolution TIF (14 MB)
|

looking west
In Nevada, Olsen Beal crews reeve cabling through an 18 part block and tackle
system for the backstay cable of the south highline crane system.
High Resolution TIF (14 MB)
|

looking northwest
Nicholson Construction continue to drill through pipe sleeves and nearly 60’
into solid rock to install post tensioning strand for the Arizona left temporary
backstay anchor block.
High Resolution TIF (14 MB)
|

looking west
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) alignment as seen from the existing US93 hairpin in Nevada.
Piers 4, 3, 2, 1 - columns are complete with their pier cap visible
above the cap falsework.
Abutment 1 – can be seen to the far right. Beyond Abutment 1, projects
the towers of the twin highline crane systems. Viewable high above the pier
caps, the 3” diameter track cables for the new highline system span the canyon
between the Nevada and Arizona highline towers.
High Resolution TIF (14 MB)
|

looking west
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) as seen from Arizona, looking towards Nevada.
In the foreground, steel girders span between Abutment 2 to Pier 15, then from
Pier 15 to Pier 14.
Across the canyon, the two white towers of the twin highline crane systems can
be seen in Nevada.
High Resolution TIF (14 MB)
|

looking south
View of half of the lower support structure of the form traveler system as it is
being prepared for installation onto the left Arch rib in Nevada. This support
structure forms the bottom of the Arch segment while concrete is placed.
High Resolution TIF (14 MB)
|

looking west
In Nevada, Olsen Beal crews reeve cabling through an 18 part block and tackle
system for the backstay cable of the south highline crane system.
High Resolution TIF (14 MB)
|

looking west
Utilizing a Manitowoc 2250 crane located in the abutment 2 area in Arizona;
Olsen Beal crews continue assembling the new highline crane system.
High Resolution TIF (14 MB)
|
Return to the Top |
Images from September & October 2007 |
Colorado River Bridge...
|

looking west
Utilizing a Manitowoc 2250 crane located in the abutment 2 area in Arizona;
Olsen Beal crews disassemble and prepare the S-70 Derrick Crane for removal and
demobilization.
High Resolution TIF (14 MB)
|

looking south
View of the new slack carriers awaiting installation on the highline crane
system.
High Resolution TIF (14 MB)
|

looking west
View of the completed Nevada towers for the new highline crane system located at
the abutment 1 area in Nevada. These towers are 335’ tall.
High Resolution TIF (14 MB)
|

looking northeast
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) as seen from Arizona, looking towards Nevada.
At the right of the picture, red temporary bracing project out from span 15 to
form the deck overhang.
Across the canyon, a Manitowoc 2250 crane located at the Nevada hairpin on
existing US93 delivers materials and workers to the top of Pier 5. Visible
beyond it are the columns of the Nevada approach and new highline crane towers.
High Resolution TIF (14 MB)
|

looking south
View of the Nevada approach columns as seen from the crest
of Hoover Dam.
From left to right:
Pier 5
– At the top, Obayashi / PSM, JV personnel stress the
pier cap transverse post tensioning.
At the bottom, formwork projects outward from the
skewback footing, forming the first two segments of the Arch.
Piers 4, 3, 2, 1 -
columns are complete with their pier cap visible above the cap falsework.
Abutment 1
– can be seen to the far right. Beyond Abutment 1, projects the tops of
the twin highline crane systems.
High Resolution TIF (14 MB)
|
Return to the Top |
Images from August 2007 |
Colorado River Bridge...
|

looking west
View of the erected steel girders for spans 15 and 16 as seen from Abutment 2 in
Arizona. The bridge deck elevation will be approximately 9” above the girders
top flange. In the background, Olsen Beal erects the Nevada towers for the new
highline crane system.
High Resolution TIF (14 MB)
|

looking west
Obayashi / PSM, JV crews continue to construct overhang brackets and formwork
onto the edge of the span 16 girder.
Across the canyon, in the abutment 1 area in Nevada, Olsen Beal crews erect the
Nevada towers for the new highline crane system. To the right of this picture,
the Manitowoc 2250 crane located at the Nevada hairpin on existing US93 is
stored in it’s laid down, non-use configuration.
High Resolution TIF (14 MB)
|

looking west
View of the Nevada approach columns of the future CO River Bridge (Mike
O'Callaghan-Pat Tillman Memorial Bridge) as seen from the existing US93 in
Arizona.
From left to right:
Pier 5 – System scaffolding encases the right column for concrete
finishing operations. At the bottom of Pier 5, formwork projects outward from
the skewback footing, forming the first two segments of the Arch.
Piers 4, 3, 2, 1 - columns are complete with their pier cap visible
above the cap falsework.
Abutment 1 – can be seen to the far right.
High Resolution TIF (14 MB)
|

looking south
Utilizing a Manitowoc M250 crane located in the abutment 1 area in Nevada; Olsen
Beal crews erect the Nevada towers for the new highline crane system. The one on
the left is currently 240’ while the one on the right is 160’ tall. When
completed these towers will top out at 335’ in height.
High Resolution TIF (14 MB)
|

looking south
Obayashi / PSM, JV utilizing the S-70 Derrick Crane at Abutment 2 in Arizona to
remove the temporary bracing between piers 14 and 15 through an opening in the
steel girder alignment. Once complete, the final girder of span 15 will be set.
At the bottom left of this picture, crews continue to form the foundation blocks
of the Arizona towers for the new highline crane system.
High Resolution TIF (14 MB)
|

looking west
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) as seen from Arizona, looking towards Nevada.
In the foreground, at the abutment 2 area, work continues on construction of the
foundation blocks of the Arizona towers for the new highline crane system, along
with the completion of girder erection for spans 15 and 16.
Across the canyon, a Manitowoc 2250 crane located at the Nevada hairpin on
existing US93 delivers materials and workers to the top of Pier 5. Visible
beyond it are the columns of the Nevada approach.
High Resolution TIF (14 MB)
|

looking northeast
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) as seen from downstream of Hoover Dam.
At the left, the Nevada approach columns (Piers 1, 2, 3, 4, & 5) are visible
awaiting steel girder placement.
To the right, the Arizona approach columns (Piers 14 & 15) can bee seen with the
girder placement nearing completion.
High Resolution TIF (14 MB)
|
Return to the Top |
Images from July 2007 |
Colorado River Bridge...
|

looking east
View of new stockpiled Cableway Crane cables located on the Nevada approach
awaiting erection.
High Resolution TIF (14 MB)
|

looking south
Nicholson Construction utilizing a Manitowoc M250 crane to transport drilling
equipment and materials to the location of the luffing guy anchor block for the
new Cableway Crane system near the Abutment 1 area.
High Resolution TIF (14 MB)
|

looking south
Utilizing the Manitowoc 2250 crane located at the Nevada hairpin on existing
US93, Olsen Beal crews construct falsework for the Pier 5 cap. Workers walk the
steel beams situated 860’ above the Colorado River.
System scaffolding encases the columns of Pier 5 to allow access for grouting
and concrete finishing operations.
To the right of Pier 5, Pier 4 can be seen.
High Resolution TIF (14 MB)
|

looking south
Obayashi / PSM, JV utilizing the S-70 Derrick Crane and a yellow man basket at
Abutment 2 in Arizona to access the Pier 14 skewback footing where crews
continue to form Arch segments.
Above the man basket, the formwork for Pier 14 pier cap can be seen. Concrete
placement for this cap took place during the night time hours on July 20, 2007.
To the left of Pier 14, completed Pier 15 along with its cap can be seen.
High Resolution TIF (14 MB)
|

looking northwest
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) as seen from Arizona, looking towards Nevada.
Across the canyon, a Manitowoc 2250 crane delivers materials and workers to the
top of Pier 5. At the bottom of Pier 5, formwork projects outward from the
skewback footing, forming the first two segments of the Arch. The blue formwork
is the inner core of the Arch form traveler system. This system will be utilized
to form the hollow inner portion of the Arch.
High Resolution TIF (14 MB)
|

looking southwest
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) as seen from the existing US93 hairpin in Nevada. From left to right:
Pier 5 – system scaffolding encases the columns for grouting and
concrete finishing operations. At the pier cap, carpenters continue to set
falsework.
Piers 4, 3, 2, 1 - columns are complete with their pier cap visible
above the cap falsework.
Abutment 1 – can be seen to the far right.
High Resolution TIF (14 MB)
|
Return to the Top |
Images from June 2007 |
Colorado River Bridge...
|

looking west
Olsen Beal crews erecting precast segments for Pier 14 left column.
Visible to the right and left are the completed columns of Pier 15.
High Resolution TIF (14 MB)
|

looking west
View of the formwork for the Pier 15 cap, ready for concrete placement.
In the background, visible between Pier 15 columns, Olsen Beal crews continue
erecting precast segments for Pier 14 left.
High Resolution TIF (14 MB)
|

looking south
View of Piers 14 and 15 as seen from the crest of the Hoover Dam.
Olsen Beal crews utilizing the S-70 Derrick crane at Abutment 2 in Arizona to
transport precast segments and erect Pier 14 left column.
To the left of Pier 14, the completed columns of Pier 15 along with the formwork
for the cap can be seen.
High Resolution TIF (14 MB)
|

looking south
Olsen Beal utilizing the Manitowoc 2250 crane located at the Nevada hairpin on
existing US93 to erect precast segments for Pier 5 left column.
High Resolution TIF (14 MB)
|

looking southwest
View of precast column segments, delivered to the Abutment 2 area, in
preparation for transport to their respective columns by the S-70 Derrick crane.
High Resolution TIF (14 MB)
|

looking south
View of the bridge alignment as seen from the crest of the Hoover Dam.
Piers 15 and 14 appear to the left in this picture, while Pier 5, 4, 3, 2, 1
appear to the right.
High Resolution TIF (14 MB)
|

looking southwest
View of the delivered steel box girders, staged at the Abutment 2 area.
High Resolution TIF (14 MB)
|

looking north
Obayashi / PSM, JV continuing to assemble the inner core form of the Arch form
traveler system. This system will be utilized to form the hollow inner portion
of the Arch.
High Resolution TIF (14 MB)
|

looking north
Subcontractor, Nicholson, drilling holes for the rock anchors of the new
highline back stay anchor located in Arizona near abutment 2.
High Resolution TIF (14 MB)
|
Return to the Top |
Images from May 2007 |
Colorado River Bridge...
|

looking east
Olsen Beal utilizing the S-70 Derrick crane at Abutment 2 in Arizona to
transport precast segments and erect Pier 14 right column.
Visible above Pier 14 is the completed columns of Pier 15.
High Resolution TIF (14 MB)
|

looking south
Olsen Beal utilizing the Manitowoc 2250 crane located at the Nevada hairpin on
existing US93 to erect precast segments for Pier 5 right column.
Visible to the right of Pier 5 is the completed columns of Pier 4.
High Resolution TIF (14 MB)
|

looking west
View of the South temporary stay cable anchor block located in Arizona near
Abutment 2.
High Resolution TIF (14 MB)
|

looking southeast
View of the bridge alignment at abutment 1.
From left to the right –
Completed Pier 2 can be seen with the formwork removed from its pier cap. Pier 1
has the falsework in place waiting for reinforcing steel / formwork to construct
the pier cap. The temporary stay cable anchor blocks are visible in the roadway
alignment to the right of the abutment. Near the yellow Grove crane, the old
Highline Crane tower foundations are being prepared for removal by blasting.
To the left of the temporary stay cable anchor blocks, the Pedestrian Access
ramp zigzags up the mountainside from the future access parking lot where the
construction office trailers are currently located.
High Resolution TIF (14 MB)
|

looking northeast
View of the bridge alignment looking towards Hoover Dam.
Left side of the picture –
Completed Pier 2, 3, and 4. Pier 5 right / left columns are in various stages of
erection. Falsework for the Arch cantilevered off of the Pier 5 skewback
footing.
Right side of the picture –
Falsework for the Arch cantilevered off of the Pier 14 skewback footing. Pier 14
right / left columns are in various stages of erection. The S-70 Derrick crane
is setting precast segments for the Pier 15 left column from Abutment 2. Pier 15
right column is competed.
High Resolution TIF (14 MB)
|

looking northwest
View of the bridge alignment looking from Abutment 2 (Arizona) towards Abutment
1 (Nevada).
Foreground: completed Pier 15 columns are wrapped in scaffolding.
Background: Falsework for the Arch is cantilevered off of the Pier 5 skewback
footing. Above the falsework, Pier 5 can be seen with crew erecting segments for
the right column. Pier 4 is visible with the pier cap falsework in place.
High Resolution TIF (14 MB)
|

looking northwest
Looking down at Pier 5 skewback footing on completed Arch segments NV01 Right
and Left. The falsework for segments 2 projects out over the canyon, ready for
formwork / reinforcing steel placement.
High Resolution TIF (14 MB)
|

looking northwest
View of the bridge alignment looking from Abutment 2 (Arizona) towards Abutment
1 (Nevada) from above Abutment 2.
Foreground: Excavations for the temporary stay cable anchor blocks are visible
in the roadway alignment near the footing of the S-70 Derrick crane. The crane
is currently setting precast segments for the erection of Pier 15 left column.
Background: Pier 5 and the Arch segments in various stages of construction. Next
are the completed Pier 4, 3, 2. Pier 1 that can be seen with the falsework in
place for the pier cap construction. Abutment 1 is visible behind Pier 1.
High Resolution TIF (14 MB)
|

looking northwest
Looking down on Olsen Beal crews preparing to set the next precast segment at
Pier 5 right as they work 230 feet above the skewback footing.
Visible below are the completed Arch segments NV01 Right and Left along with the
falsework for segments 2.
High Resolution TIF (14 MB)
|
Return to the Top |
Images from April 2007 |
Colorado River Bridge...
|

looking east
Olsen Beal utilizing the S-70 Derrick Crane at Abutment 2 in Arizona to
transport precast segments and erect Pier 15 right and left columns.
Visible below Pier 15 is the skewback footing of Pier 14 with the falsework for
the Arch protruding outward.
High Resolution TIF (14 MB)
|

looking west
View of the South temporary stay cable anchor block located in Nevada near
Abutment 1.
High Resolution TIF (14 MB)
|

looking west
View of delivered concrete being cooled with liquid Nitrogen prior to placement
for construction of the Arch segment NV01-RT.
High Resolution TIF (14 MB)
|

looking southwest
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) alignment as seen from the existing US93 hairpin in Nevada.
Abutment 1 in final stages of construction with the blockouts for the tie back
anchors remaining to be filled.
Pier 1 is shown with falsework for the pier cap in place.
Pier 2 can be seen with the completed pier cap.
Pier 3 is visible with the completed pier cap along with climbing
scaffolding surrounding the columns.
Pier 4 is visible with the completed pier cap.
High Resolution TIF (14 MB)
|
Return to the Top |
Images from March 2007 |
Colorado River Bridge...
|

looking west
Workers from Jake’s Crane prepare for the removal of the counter weights from
the
Link Belt TG1900 erected on the
Pier 15 left foundation. This worker is attaching hoisting slings onto the
weights wile perched nearly 865’ above the Colorado River.
High Resolution TIF (14 MB)
|

looking south
Obayashi / PSM, JV utilizing a
Manitowoc 2250 crane to construct / access Piers 3 and 4 from
the Nevada
hairpin on existing US93.
High Resolution TIF (14 MB)
|

looking west
View of the bridge alignment as seen from Arizona towards
Nevada.
Piers 1, 2, 3, 4, 5 in various
stages of completion. Formwork for Arch segments NV01N and NV01S can be
seen cantilevered off of the Pier 5 (NV skewback) footing.
High Resolution TIF (14 MB)
|

looking southwest
Jake’s Crane utilizing the S-70 Derrick Crane at Abutment
2 in Arizona to dismantle the Link Belt TG1900 from the Pier 15 left
foundation.
Visible to the left of the crane
is Pier 15 right in partial stage of completion.
High Resolution TIF (14 MB)
|

looking north
Crane close-up.
High Resolution TIF (14 MB)
|

looking north
Workers from Jake’s Crane utilizing the S-70 Derrick Crane at Abutment 2 in
Arizona to dismantle the
Link Belt TG1900 from the Pier 15
left foundation. Crews are removing the boom section and transporting it
to the laydown area on the Arizona approach roadway.
High Resolution TIF (14 MB)
|

looking east
View of the future CO River Bridge (Mike
O'Callaghan-Pat Tillman Memorial Bridge) alignment as
seen from Nevada, looking towards Arizona.
Abutment 1 in final stages of construction with the blockouts for the
tie back anchors remaining to be filled.
Pier 1 is shown with falsework for the pier cap in place.
Pier 2 can be seen with formwork for the pier cap in place.
Concrete placement for the cap was performed on August 21, 2006.
Pier 3 is visible with formwork for the pier cap in place.
Concrete placement for the cap was performed on March 27th.
Pier 4
is visible with formwork for the pier cap in place. Ironworkers are placing
reinforcing steel for the cap.
High Resolution TIF (14 MB)
|
Return to the Top |
Images from February 2007 |
Colorado River Bridge...
|

looking northwest
Dielco Crane assembles and attaches the luffing jib to the Manitowoc 2250 crane
at the existing US93 near the hairpin in Nevada.
High Resolution TIF (14 MB)
|

looking northDielco Crane assembling a Manitowoc 2250 crane
to be utilized at the existing US93 near the hairpin in Nevada.
High Resolution TIF (14 MB)
|

looking south
Obayashi / PSM, JV personnel constructing falsework for the Pier 4 pier cap in
the work access area of the existing US93 near the hairpin in Nevada.
High Resolution TIF (14 MB)
|

Overall View #1.
High Resolution TIF (14 MB)
|

Overall View #2
.
High Resolution TIF (14 MB)
|

looking west
Obayashi / PSM, JV and Olsen Beal personnel assembling the
70 foot mast for the S-70 Derrick Crane near Abutment 2 in Arizona.
High Resolution TIF (14 MB)
|

looking southwest
Obayashi / PSM, JV and Olsen Beal prepare to raise and install the 70 foot mast
for the S-70 Derrick Crane near Abutment 2 in Arizona.
High Resolution TIF (14 MB)
|

looking east
View of the future CO River Bridge (Mike O'Callaghan-Pat
Tillman Memorial Bridge) alignment as seen from Nevada, looking towards Arizona.
Visible to the lower left of this photograph is the nearly completed pedestrian
access ramp as it zigzags up the mountain side onto the alignment near Abutment
1.
High Resolution TIF (14 MB)
|

looking north
View of the bridge alignment as seen from downstream of the Hoover Dam.
Left Center: Piers 1, 2, 3, 4, 5 in various stages of completion. Formwork for
Arch segments NV01N and NV01S can be seen cantilevered off of the Pier 5 (NV
skewback) footing.
Right Center: Pier 14 (AZ skewback) footing, Pier 15, and abutment 2 are
visible. The Link Belt TG1900 Tower Crane remains erected on the left footing
foundation of Pier 15.
High Resolution TIF (14 MB)
|

looking northeast
Ladd & Associates place back fill
material at Abutment 1 in Nevada.
High Resolution TIF (14 MB)
|

looking south
Obayashi / PSM, JV utilizing a Manitowoc 2250 crane to construct / access Piers
3 and 4 from the Nevada hairpin on existing US93.
High Resolution TIF (14 MB)
|

looking south
Subcontractor, Nicholson, drilling holes for the rock
anchors on the north temporary backstay anchor block in Nevada near abutment 1.
High Resolution TIF (14 MB)
|
Return to the Top |
Images from January 2007 |
Colorado River Bridge...
|

looking west
Obayashi / PSM, JV personnel stockpiling system scaffolding materials in the
work access area of the existing US93 near the hairpin in Nevada.
High Resolution TIF (14 MB)
|

looking east
View of the S-70 Derrick Crane bracing to be erected near
Abutment 2 in Arizona. This crane will be utilized to erect Piers 14 and 15 and
construct portions of the Arch from the Arizona side of the canyon.
High Resolution TIF (14 MB)
|

Obayashi / PSM, JV crews place concrete to construct the south Back Stay Anchor
block near Abutment 1 in Nevada.
High Resolution TIF (14 MB)
|

looking west
Obayashi / PSM, JV utilizing a Grove GMK6350 truck crane to
remove system scaffolding from Pier 2 left.
From left to right appear Pier 4 left with system scaffolding erected
around its column, Pier 3 has climbing scaffolding attached to allow
access for grouting / finishing operations,
Pier 2 is currently having the system scaffolding removed. Behind Pier 2,
Pier 1 and Abutment 1 can be seen.
High Resolution TIF (14 MB)
|
Return to the Top |
Images from November/December 2006 |
Colorado River Bridge...
|

looking west
View of the bridge alignment looking from Abutment 2 (Arizona) towards Abutment
1 (Nevada).
Foreground: Reinforcing steel for the Abutment 2
backwall protrudes upwards. Further out, Pier 15 Right in the current
erection stage while the Link Belt TG1900 tower crane remains erected on Pier
15 Left footing.
Background: Pier 5 is in the erection stage. Behind Pier 5, Pier 4
is visible with the pier cap falsework in place.
High Resolution TIF (14 MB)
|

looking north
View of Nevada Approach piers as seen from the Colorado
River elevation just downstream of the Hoover Dam. Visible from the left to the
right are Piers 1 through 5. The formwork for the arch starter segments is
cantilevered off of the Pier 5 skewback footing, protruding out over the canyon
wall. Temporary bracing spans between Piers 2 to Pier 4. Once Pier 5 is erected
to the temporary bracing elevation, additional sections will be set to connect
to Pier 4.
High Resolution TIF (14 MB)
|

looking north
Obayashi / PSM, JV and Cross Marine Projects utilizing a crane and dive team to
remove fallen Cableway Crane System debris from the Colorado River. Crews were
staged at the river’s edge on top of the Hoover Dams’ Nevada spillway tunnel
structure.
High Resolution TIF (14 MB)
|

looking southeast
View of Arizona Approach as seen from the existing US93 near
the hairpin in Nevada.
High Resolution TIF (14 MB)
|

looking southwest
Obayashi / PSM, JV utilizing a Grove GMK6350 truck crane to access Piers 3
through 5 from the existing US93 at the hairpin turn in Nevada. From left to
right appear Pier 4 with its pier cap falsework partially constructed,
Pier 3 has climbing scaffolding attached to allow access for grouting /
finishing operations, and Pier 2 has system scaffolding erected around
its columns to allow access to the pier cap. Behind Pier 2, Pier 1 and
Abutment 1 can be seen.
High Resolution TIF (14 MB)
|

looking southwest
View of Hoover Dam and Nevada Approach as seen from the
Hoover Dam visitor parking area in Arizona.
High Resolution TIF (14 MB)
|
Return to the Top |
Images from October 2006 |
Colorado River Bridge...
|

looking southeast
Obayashi / PSM, JV personnel loading the last segments of the collapsed
South Cableway Crane towers at the Abutment 1 area in Nevada.
High Resolution TIF (14 MB)
|

Obayashi / PSM, JV personnel are utilizing a crane to access Pier 4 to remove a
temporary protection beam from the side of the columns.
To the right of Pier 4, visible is Pier 3 with access scaffolding projecting up
from the ground.
Behind Pier 3, Pier 2 can be seen with its completed pier cap in place.
High Resolution TIF (14 MB)
|

looking east
View of Abutment 1 with backfilling operation nearing
completion.
High Resolution TIF (14 MB)
|

looking west
Ladd & Associates utilizing hoppers to transport backfill material for the
backfilling of Abutment 2.
High Resolution TIF (14 MB)
|

looking west
View of the approach spans looking from Pier 5 to Abutment 1 as seen from the
Nevada hairpin on existing US93.
High Resolution TIF (14 MB)
|
Return to the Top |
Images from September 2006 |
Colorado River Bridge...
|

View of the collapsed North and South Cableway Crane system looking from Nevada
towards Arizona.
High Resolution TIF (14 MB)
|

View of the collapsed North and South Cableway Crane system at Abutment 2 area
in Arizona.
High Resolution TIF (14 MB)
|
Return to the Top |
Images from August 2006 |
Colorado River Bridge...
|

View of the Colorado River Bridge alignment looking East from Nevada towards
Arizona.
Pictured from left to right:
Abutment 1 in final stages of construction.
Pier 1 is shown with falsework for the pier cap in place.
Pier 2 is shown with pier cap formwork in place ready for concrete
placement.
Pier 3 is shown with falsework for the pier cap in place.
Pier 4 is in the erection stage awaiting falsework for the pier cap.
Pier 5 right is in the erection stage
High Resolution TIF (14 MB) |

View of the bridge alignment looking East from Nevada towards the Arizona side
of the canyon.
From the bottom to the top:
Pier 14 Skewback footing is complete. On the temporary work platform,
Nicholson Construction is drilling for the temporary tie back anchors through
the footing into the canyon wall.
A Link Belt TG1900 tower crane is erected on Pier 15
left footing. Pier 15 right is in its initial stages of erection
with several segments placed.
The formwork for Abutment 2 appears near the center of this
picture.
High Resolution TIF (14 MB) |

The bridge alignment looking West from Arizona towards the Nevada approach
spans. Pictured from bottom to top.
Visible is the formwork for the Arch starter segments attached to the Pier
5 Skewback footing. Above the footing, crews on Pier 5
continue to erect precast segments. All of the precast segments for Piers 1
through 4 have been erected and the pier caps are in various stages of
construction. Grey colored temporary bracing can been seen attached between
Pier 4
and Pier 3 and between Pier 3 and
Pier 2. Overhead, the cableway cranes provide personnel access and
material deliveries to the pier columns.
High Resolution TIF (14 MB) |

Looking East
Ladd & Associates in the process of backfilling the Abutment 1. Projecting on an
angle through the right retaining wall and the abutment are the tie back
anchors. Visible through Abutment 1 backwall reinforcing steel is the falsework
for the Pier 1 pier cap and the formwork for the Pier 2 pier cap.
High Resolution TIF (14 MB) |

Looking SouthwestView of the Abutment 2 stem wall in preparation
for concrete placement after formwork and reinforcing steel have been
constructed.
High Resolution TIF (14 MB) |

Looking West
View of the approach spans looking from Pier 4 to Abutment 1 as seen from the
Nevada hairpin on existing US93.
High Resolution TIF (14 MB) |
Return to the Top |
Images from July 2006 |
Colorado River Bridge...
|

(looking east)View of the Colorado River Bridge alignment
looking from Nevada towards Arizona. Pictured from left to right:
Abutment 1 in final stages of construction. Formwork for panels 1 and 3 of the
nearly 57’ tall retaining wall being placed.
Pier 1 is shown with falsework for the pier cap in place.
Pier 2 is shown with falsework for the pier cap in place.
Pier 3 is in the erection stage.
Pier 4 is in the erection stage awaiting temporary wind bracing placement.
High Resolution TIF (14 MB)
|

(looking south)Obayashi / PSM, JV personnel placing concrete
for the Pier 14 footing (Arizona skewback). Nearly 2200 cubic yards of concrete
was placed, all of which was pumped though the twin 700’ long pipes (slick line)
extending from the Abutment 2 area into Pier 14 which can be seen bolted to the
excavation wall.
Reinforcing steel for the South arch is visible extending out of the face of the
formwork.
High Resolution TIF (14 MB)
|

(looking east)Obayashi / PSM, JV personnel placing concrete
for the Pier 14 footing (Arizona skewback). Two 32 meter concrete placing booms
were utilized to accurately distribute the concrete into the formwork.
Reinforcing steel for the North arch is visible extending out of the face of the
formwork.
High Resolution TIF (14 MB)
|

(looking south)Obayashi / PSM, JV personnel working late
into the night placing concrete for the Pier 14 footing (Arizona skewback).
High Resolution TIF (14 MB)
|

(looking southwest)View of the Nevada approach columns
looking from Pier 4 to Abutment 1.
High Resolution TIF (14 MB)
|

(looking east)At the Liquid Nitrogen (LN2) cooling station,
Liquid Nitrogen is being injected into concrete mixer trucks to cool the freshly
batched concrete.
High Resolution TIF (14 MB)
|

(looking southwest)Olsen Beal utilizing the two cableway
cranes in tandem to erect the temporary bracing between Pier 2 and 3.
High Resolution TIF (14 MB)
|
Return to the Top |
Images from June 2006 |
Colorado River Bridge...
|

(looking east)View of the Colorado River Bridge alignment
looking from Nevada towards Arizona. Pictured from left to right:
Abutment 1 in final stages of construction. Formwork for
the second lift on the retaining wall being placed.
Pier 1 is shown with falsework for the pier cap in place.
Pier 2 is erected to pier cap elevation.
Pier 3 is in the erection stage awaiting temporary wind
bracing placement.
Pier 4 right, Olsen Beal crews utilizing the cableway
crane to set a precast segment.
High Resolution TIF (14 MB)
|

(looking southeast)View of the bridge alignment looking
towards the Arizona side of the canyon. From the bottom to the top:
Pier 14 Skewback footing formwork is completed awaiting concrete placement. As
seen to the right of the excavation, twin 700’ long pipes (slick line) extend
from the Abutment 2 area into Pier 14 for placement of concrete by pumping.
A Link Belt TG1900 tower crane is erected on Pier 15 left footing.
The formwork for Abutment 2 appears near the center of this picture.
High Resolution TIF (14 MB)
|

(looking southeast)
Precast column segments staged
near abutment 1 awaiting placement for the approach span columns.
High Resolution TIF (14 MB)
|

(looking southwest)Left: Olsen Beal personnel
utilizing the cableway crane to set another segment for the Pier 4 right column.
Center: Crews from Jake’s Crane dismantling the Link Belt TG1900 tower crane
erected on Pier 4 left footing.
Right: Temporary scaffolding is attached to the sides of Pier 3 left column to
provide access during final stages of erection. This scaffolding is utilized
during segment erection and subsequent post tensioning bar grouting operations.
High Resolution TIF (14 MB)
|

View of the approach spans looking from Pier 3 to Abutment 1.
High Resolution TIF (14 MB)
|

(looking northwest)View of the approach spans looking from
Pier 3 to Abutment 1.
High Resolution TIF (14 MB)
|

(looking south)Close up view of Olsen Beal personnel setting
a precast segment for the Pier 4 right column.
High Resolution TIF (14 MB)
|

(looking northwest)The bridge alignment looking from Arizona
straight towards the Nevada approach spans. Pictured from bottom to top.
Nicholson Construction drilling for the temporary tie back anchors through the
Pier 5 Skewback footing into the canyon wall. Crews on Pier 4 right
erecting precast segments. The cableway crane lowering the next segment for
placement is visible. Temporary scaffolding can been seen attached to Pier 3
left. Pier 2
is completed up to pier cap elevation. Behind pier 2, barely visible is the
scaffolding on Pier 1 and the partially constructed
Abutment 1.
High Resolution TIF (14 MB)
|
Return to the Top |
Images from May 2006 |
Colorado River Bridge...
|

View of the excavation at Pier 14.
(looking down)Harris Rebar personnel placing reinforcing
steel for the Pier 14 footing (Arizona skewback). Visible along the excavation
walls are rock bolts installed to provide slope stability.
High Resolution TIF (14 MB)
|

View of the formwork at Pier 14.
(looking down)Harris Rebar personnel placing reinforcing
steel for the Pier 14 footing (Arizona skewback).
High Resolution TIF (14 MB)
|

View of the excavation and formwork at Pier 14.
(looking east)View of the excavation and formwork reinforcing
steel placement for the Pier 14 footing (Arizona skewback).
High Resolution TIF (14 MB)
|

The precast yard
(Boulder City, Nevada).
(looking west)Obayashi / PSM, JV nearing completion of
casting precast column segments at the precast yard located near Boulder City,
Nevada.
High Resolution TIF (14 MB)
|

Abutment 2
(looking northeast)View of the excavation and formwork
placement at Abutment 2.
High Resolution TIF (14 MB)
|

Abutment 2.
(looking down)Another view of the excavation and formwork
placement at Abutment 2.
High Resolution TIF (14 MB)
|

(overview - looking west)
High Resolution TIF (14 MB)
|

(zoomed in - looking west)
High Resolution TIF (14 MB) |
Lower Center: Olsen Beal erecting precast segments to
construct Pier 1 left.
Lower Center Background: Formwork can be seen for Abutment 1.
Lower Foreground: Temporary scaffolding hangs from the sides of Pier 2 Right
and Left columns. This scaffolding is utilized during segment erection and
subsequent post tensioning bar grouting operations.
|

Obayashi/PSM, JV Carpenters
(looking north)Obayashi / PSM, JV carpenters constructing
falsework / formwork for the cast-in-place pier caps.
High Resolution TIF (14 MB)
|

View of the bridge alignment
looking from Nevada to Arizona .
(looking northwest)View of the bridge alignment looking at
the Nevada approach spans. Depicted near the center left are the partially
constructed Abutment 1, completed Pier 1 right column, partially completed Pier
2 right, Pier 3, and Pier 4 right columns. At the lower center of this view is
the completed Pier 5 Skewback footing just below the existing US93 roadway
alignment.
High Resolution TIF (14 MB)
|

The future bridge alignment.
(looking east)View of the Colorado River Bridge alignment
looking from Nevada towards Arizona. Near the lower left, the excavation for the
future Pedestrian Plaza access trail leading to Abutment 1 zigzags up from the
future parking lot area .
High Resolution TIF (14 MB)
|

View of the bridge alignment
looking from Arizona to Nevada. (looking east)Aerial view of
the future bridge alignment taken from Abutment 1 (Nevada) looking towards
Abutment 2 (Arizona). Shown at the bottom center of this picture is the competed
excavation for Pier 14 (Arizona skewback).
High Resolution TIF (14 MB)
|
Return to the Top |
Images from April 2006 |
Colorado River Bridge...
|

Rock Anchors in the backwall
(looking up)View of the installed rock anchors of the
excavated backwall of Pier 14 (Arizona Skewback) taken from the footing
elevation, looking up. The top of this Ľ:1 excavated face is 146’ above the
footing elevation.
At the right of this picture is the temporary ladder system in the process of
being constructed and bolted to the excavated wall.
High Resolution TIF (14 MB)
|

View of the bridge alignment looking towards Abutment 1 (Nevada).
(looking west)Lower Center: Formwork and reinforcing
steel of the Pier 5 Skewback footing.
Center: Erected precast segments of Piers 1, 2, and 3 right columns in various
stages of construction.
Upper Center: Formwork and reinforcing steel of partially constructed Abutment
1.
Top: View of the cableway crane systems. The South cableway (left) is completed
while the North (right) is in the process of being constructed. Visible to the
left of the tower crane at the lower center of the picture is the second 3”
cable coming across the canyon.
High Resolution TIF (14 MB)
|

Location for Abutment 2
(looking east)Rock excavation for Abutment 2 completed .
High Resolution TIF (14 MB)
|

Pier 5 Formwork
(looking southwest)Obayashi / PSM, JV completing formwork for
the Pier 5 Skewback footing.
High Resolution TIF (14 MB) |

Rock anchors at Pier 14
(looking down)View of the installed rock anchors of the
excavated faces of Pier 14 (Arizona Skewback).
Right: A temporary ladder system is in the process of being constructed and
bolted to the excavated wall to allow personnel access to the footing.
Lower Left: Work crews take a lunch break and sit on the excavation floor.
High Resolution TIF (14 MB)
|

Concrete Pump Trucks
(looking southwest)Obayashi / PSM, JV utilizing two 58 meter
pump trucks to place 2,030 cubic yards of concrete, supplied by Casino Ready
Mix, for the Pier 5 Skewback footing. Placement operations were staged on the
existing US-93 and began at 6:30PM, finishing at 3:30PM the following afternoon.
High Resolution TIF (14 MB) |

Placing Concrete for Pier 5
(looking down)View of the concrete placement operation for the Pier 5
Skewback footing.
High Resolution TIF (14 MB)
|
Return to the Top |
Images from March 2006 |
Colorado River Bridge...
|

Preparing for the Lift
(looking south)Olsen Beal personnel rigging the precast
segment lifting jib onto a segment in preparation for lifting it over the canyon
for placement.
High Resolution TIF (14 MB)
|

Unloading
(looking south)View of a precast segment being unloaded off
of a transport trailer in Nevada near Abutment 1.
High Resolution TIF (14 MB) |

Towering Above
(looking west)Olsen Beal working on construction of the North
cableway crane in Nevada. These temporary towers rise 330’ above the future
roadway elevation.
High Resolution TIF (14 MB)
|

The Future Pedestrian Plaza
(looking northwest)Ladd & Associates excavating for the
Pedestrian Plaza access trail leading from the future parking lot to Abutment 1.
High Resolution TIF (14 MB) |

Pier 5 formwork & reinforcing steel
(looking down)View of the Pier 5 Skewback formwork and
reinforcing steel looking down from the existing US-93 roadway elevation. The
Colorado River flows approximately 650 feet below the excavated ledge on which
the Skewback footing is being constructed.
High Resolution TIF (14 MB)
|

Building the North Cableway Crane
(looking west)Olsen Beal constructing the North cableway
crane in Arizona.
High Resolution TIF (14 MB) |

View of the bridge alignment looking
towards Abutment 1 (Nevada).
(looking southwest)Lower Center: Formwork and reinforcing steel of the
Pier 5 Skewback
footing in preparation for concrete placement.
Center: Olsen Beal erecting segments at Pier 2 right column.
Upper Center: Formwork and reinforcing steel of partially constructed
Abutment 1.
Top: – View of the cableway crane systems.
High Resolution TIF (14 MB)
|
Return to the Top |
Images from February 2006 |
Colorado River Bridge...
|

Precast Pier
(looking southwest)Olsen Beal utilizing the cableway crane to
transport and lower a precast segment section for Pier 3 right where it will be
attached to the sections below.
High Resolution TIF (14 MB)
|

Cranes
(looking west)View of the roadway alignment and two cableway
cranes at Abutment 2 in Arizona.
High Resolution TIF (14 MB) |

Future Bridge Alignment
(looking east - towards Abutment 2; Arizona)
Lower Left: Ladd & Associates drilling holes for the tie back anchors at
Abutment 1. Behind the drill rig is the Abutment stem wall under construction.
Lower Center: Visible below the tower crane are the stacked precast pier
segments for Pier 2 Right.
Upper Center Right: Completed excavation of Pier 14 (Arizona Skewback). A
Caterpillar 320C Trackhoe rests on the excavation floor, approximately 600 feet
above the waters of the Colorado River below.
High Resolution TIF (14 MB)
|

Transporting precast pier sections
with the Cranes
(looking southwest)Top right: View of the partially
constructed Abutment 1.
Upper Center: View of the erected precast segments of Pier 2 right column.
Visible to the right of this is the footing of Pier 2 left.
Lower Left: Olsen Beal utilizing the two cableway crane to transport and lower
a precast segment section for Pier 3 right. Construction personnel stand on the
footing of Pier 3 left viewing the operation.
High Resolution TIF (14 MB) |

Over the River
(looking southeast)View of an 80 foot wide preassembled
reinforcing steel mat being transported across the river by the cableway crane
from the Abutment 2 area to the Pier 5 Skewback where it will be placed for
construction of the footing.
High Resolution TIF (14 MB)
|

Placing the Reinforcing Steel Mat
(looking south)Paradise Steel personnel direct an 80 foot
wide preassembled reinforcing steel mat for Pier 5 footing into position as it
is being lowered by the cableway crane.
High Resolution TIF (14 MB) |
Return to the Top |
Images from January 2006 |
Colorado River Bridge...
|

Future Bridge Alignment
(looking northwest)View of the bridge alignment looking
towards Abutment 1 (Nevada).
Lower Center: Footings of Pier 2 left and right.
Center: Stained Shotcrete constructed for stabilization of the existing rock.
To the left of the Shotcrete are the footings of Pier 1 left and right.
Upper Left: The temporary towers of the cableway crane. Near the bottom of
these towers, reinforcing steel projects upwards for Abutment 1.
High Resolution TIF (14 MB)
|

Obayashi/PSM, JV Constructing Formwork
(looking northwest)Overall view of Obayashi / PSM, JV
personnel constructing formwork for the footings of Pier 3 left and right.
Near the lower left, a shadow of a man basket appears on the canyon wall. This
picture was taken from this man basket as it was suspended nearly 700 feet above
the Colorado River by the Link Belt TG1900 Tower Crane erected on Pier 4’s left
foundation.
High Resolution TIF (14 MB) |

Constructing Formwork
(looking west)Obayashi / PSM, JV personnel constructing
formwork and reinforcing steel for the footings of Pier 3 left and right. Shown
in the top left of this picture are rock anchors installed in the excavation
walls.
High Resolution TIF (14 MB)
|

Constructing Formwork
(looking west)
Another photo of Obayashi / PSM, JV personnel constructing formwork and
reinforcing steel for the footings of Pier 3 left and right. To the top
left of this picture are the corrosion protection covers of the installed rock
anchors in the excavation walls.
High
Resolution TIF (14 MB) |

Work on Piers 3 & 4
(looking down)Top Right: The Link Belt TG1900 Tower
Crane erected on the left footing foundation of Pier 4.
Lower Right: View the completed excavation for Pier 4 right.
Lower Left: Ladd & Associates utilizing a trackhoe to remove fallen rock
contained by a Rock Fall Containment system constructed near Pier 4.
Upper Left: Obayashi / PSM, JV personnel constructing formwork for the footings
of Pier 3 left and right.
High Resolution TIF (14 MB)
|

View of the Bridge Alignment
(looking north)View of the bridge alignment taken from
downstream of Hoover Dam. Nevada approach appears to the left with Arizona to
the right. Visible near the top of this picture is the twin 3” cables spanning
the canyon for one of two cableway cranes.
High Resolution TIF
(14 MB)
|

Excavation for Pier 5 Completed
(looking north)View the completed excavation for Pier 5
(Nevada skewback). The excavated face shown is approximately 100’ high.
Corrosion protection covers of the installed rock anchors in the excavation
walls are visible in the excavated rock face.
Hoover Dam appears near the lower left of the picture.
High Resolution TIF (14 MB)
|

Cableway Crane Tower
(looking south)View of the south Cableway Crane tower in
Arizona depicting the pull cable slack carriers, hoist trolley, and tower
stabilization cables.
High Resolution TIF (14 MB) |

Pulley System
(looking east)View of the twin 14 part pulley system of the
south Cableway Crane tower in Nevada. These pulleys apply tension to the twin 3”
highline cables that span the canyon.
High Resolution TIF (14 MB)
|

Skagit Hoist
(looking south)View of the Arizona Skagit hoist used for
erection of the Cableway Crane system.
High Resolution TIF (14 MB) |

Future Bridge Alignment
(looking west)View of the future bridge alignment taken from
Abutment 2 (Arizona) looking towards Abutment 1 (Nevada).
Foreground: The Link Belt TG1900 Tower Crane erected on the left footing of
Pier 15.
Background: Visible are the footings and excavations for Abutment 1, Piers 1
through 5 (Nevada skewback), along with the Link Belt TG1900 Tower Crane erected
on the left footing of Pier 4.
High Resolution TIF (14 MB)
|

Olsen Beal Personnel
(looking south)Olsen Beal personnel winding cable onto a
temporary reel during the construction of the cableway crane in Arizona.
High Resolution TIF (14 MB) |
Return to the Top |
Images from December 2005 |
Colorado River Bridge...
|

Future Bridge Alignment
(looking east)View of the bridge alignment from Abutment 1
(Nevada) looking towards Abutment 2 (Arizona). Foreground: Obayashi /
PSM, JV constructing formwork and placing reinforcing steel for Abutment 1.
Background: Ongoing excavations for Pier 14 (Arizona skewback) and Abutment
2 along with the towers of the temporary cableway crane.
High Resolution TIF (14 MB)
|

Nevada Approach Pier Excavations
(looking northwest)View of the bridge alignment taken from
downstream of Hoover Dam depicting the Nevada approach pier excavations.
The Link Belt TG1900 Tower Crane is erected on Pier 4 left foundation.
High Resolution TIF (14 MB) |

Arizona Approach Pier Excavations
(looking northeast)View of the bridge alignment taken from
downstream of Hoover Dam depicting the Arizona approach pier excavations.
The Link Belt TG1900 Tower Crane is erected on Pier 15 left foundation.
High Resolution TIF (14 MB)
|

Olsen Beal at work
(looking west)Olsen Beal constructing the cableway crane in
Arizona.
High Resolution TIF (14 MB) |

Stringing a line
(looking south)Upper right: View of the helicopter
transporting a half-inch cable across the canyon for stringing of the cableway.
Barely visible below the helicopter is a hoop in the line used to grab once it
reaches the Nevada side. The second helicopter is being utilized as a
spotter.
High Resolution TIF (14 MB)
|

Downstream of the Dam
(looking north)View of the bridge alignment taken from
downstream of Hoover Dam. Nevada approach appears to the left with Arizona
approach to the right. Visible near the top of this picture is the twin 3"
cables spanning the canyon for one of two cableway cranes.
High Resolution TIF (14 MB) |
Return to the Top |
Images from November 2005 |
Colorado River Bridge...
|

Future Bridge Alignment
(looking east)View of the future bridge alignment taken from
Abutment 1 (Nevada) looking towards Abutment 2 (Arizona). Shown are the ongoing
excavations for Pier 14 (Arizona skewback) and Abutment 2. In the
background of this picture, are the towers of the temporary cableway crane which
will span the canyon and be utilized for construction of the bridge.
High Resolution TIF (14 MB)
|

Readying the Formwork
(looking east)Obayashi / PSM, JV personnel ready column
segment formwork in preparation for concrete placement. Segments are wet cast
against the next lower piece to assure a good match cast joint.
High Resolution TIF (14 MB) |

Completed Precast Column Segments
(looking west)View of the completed precast column segments
stored and ready for shipment at the Obayashi / PSM, JV precast yard located
near Boulder City, Nevada.
High Resolution TIF (14 MB)
|

Excavation work continues
(looking west)Foreground: View of the ongoing
excavations for Pier 5 (Nevada Skewbasdk) and Pier 3, and completed footings of
Piers 1 and 2.
Background: The towers of the temporary cableway crane
which will span the canyon and be utilized for construction of the bridge.
High Resolution TIF (14 MB) |

Excavations at the Arizona Skewback
(looking east)Foreground: Ladd & Associates continuing
excavation for Pier 14 (Arizona Skewback) and Abutment 2 and installing rock
containment fencing on the canyon wall at Pier 14.
Background: The towers of the temporary cableway crane
which will span the canyon and be utilized for construction of the bridge.
High Resolution TIF (14 MB)
|

Fine grading activities
(looking south)Ladd & Associates utilizing a trackhoe and
rock hammer to fine grade the excavation of Pier 5 (Nevada skewback).
Bottom left in this picture is the rock containment fencing installed on the
canyon face.
High Resolution TIF (14 MB) |

Rock Anchors and a Temporary Ladder
(looking north)View of the installed rock anchors of the
north rock excavated face of Pier 5 (Nevada Skewback). A temporary ladder
system is in the process of being bolted to this wall to allow personnel access
to the footing from the Nevada Hairpin area.
High Resolution TIF (14 MB)
|

Ladd & Associates continue grading activites
(looking down)Ladd & Associates utilizing a trackhoe and rock
hammer to fine grade the excavation of Pier 5 (Nevada skewback). Top left in
this picture is the Colorado River, approximately 650-feet below the level of
this excavation. Top right is a temporary rock containment structure.
High Resolution TIF (14 MB) |
Return to the Top |
Images from October 2005 |
Aerial Photos of the New US 93...
|

New Arizona Alignment
(looking west)Aerial view of the new alignment in Arizona
from Station 270+00 to 198+00 including the interim US 93 roadway.
Foreground: View of the Arizona Interchange and associated ramps, including
the Sugarloaf Mountain TIOP Bridge.
Background: Sugarloaf Mountain Bridge.
High Resolution TIF (14 MB)
|

US 93 New Alignment
(looking north)Aerial view of the new alignment from Station
63+00 to 123+00.
Bottom Left: Hoover Dam Canyon Bridge.
Top Right: Hoover Dam Lower Portal Access Road Overpass (Structure H-2701), the
Hoover Dam BOR Warehouse Old US 93 Overpass (Structure H-2702), and the Hoover
Dam Old US 93 Overpass (Structure H-2703).
High Resolution TIF (14 MB) |

Nevada Interchange & Ramps
(looking north)Aerial view of the Nevada Interchange and
associated ramps, including the Hoover Dam Interchange Bridge (Structure H-2699)
and the Gold Strike Canyon Access Road.
High Resolution TIF (14 MB)
|

Hoover Dam Canyon Bridge
(looking west)Aerial view of the new alignment from Station
75+00 to 26+93.
Foreground: Hoover Dam Canyon Bridge (Structure H-2700).
Background: View of the Nevada Interchange and associated ramps, including the
Hoover Dam Interchange Bridge (Structure H-2699) and the Gold Strike Canyon
Access Road.
High Resolution TIF (14 MB) |

Aerial View of 3 new Overpasses
(looking west)Aerial view of the new alignment from Station
123+00 to 71+00 including the Hoover Dam Old US 93 Overpass (Structure H-2703),
the Hoover Dam BOR Warehouse Old US 93 Overpass (Structure H-2702), and the
Hoover Dam Lower Portal Access Road Overpass (Structure H-2701).
High Resolution TIF (14 MB)
|

The New Alignment tying into the OldAerial view of the new
alignment as it ties into the existing US 93 in Nevada.
High Resolution TIF (14 MB) |
Colorado River Bridge...
|

Obayashi / PSM, JV Precast Yard
(looking east)Aerial view of the Obayashi / PSM, JV precast
yard located near Boulder City, Nevada. Four hundred-forty (440) precast
segments, each weighing approximately 35 tons, will be constructed for the
bridge approach and spandrel columns.
High Resolution TIF (14 MB)
|

Aerial View of Future Bridge AlignmentAerial view of the new
alignment looking from Arizona towards Nevada showing the location of the future
Colorado River Bridge.
High Resolution TIF (14 MB) |

Aerial View of Future Bridge Alignment
(looking west)Aerial view of the future bridge alignment
taken from Abutment 2 (Arizona) looking towards Abutment 1 (Nevada). Shown
are the ongoing excavations for Pier 5 (Nevada skewback) and Pier 3, and
completed footings of Piers 1 and 2 along with the excavation for Abutment 1
footing.
High Resolution TIF (14 MB)
|

Excavations for Pier 14 & Abutment 2
(looking east)Aerial view of the future bridge alignment
taken from Abutment 1 (Nevada) looking towards Abutment 2 (Arizona). Shown
are the ongoing excavations for Pier 14 (Arizona Skewback) and Abutment 2.
In the foreground, a crane is erecting the towers of the temporary cableway
crane which will span the canyon and be utilized for construction of the bridge.
High Resolution TIF (14 MB) |

Erection of temporary cableway crane towers.
(looking southeast)Aerial view of the future bridge alignment
taken from Abutment 1 (Nevada) looking towards Abutment 2 (Arizona).
Subcontractor, Olsen Beal, completing erection of the temporary cableway crane
towers in Arizona. Shown at the bottom of this picture is the on-going
excavation for Pier 14 (Arizona Skewback) being performed by Ladd & Associates.
High Resolution TIF (14 MB)
|
Nevada Approach...Completed!
|

Lower Portal Access Road Overpass (looking north)View of
the completed Hoover Dam Lower Portal Access Road Overpass (Structure H-2701).
High Resolution TIF (14 MB)
|

BOR Warehouse Old US 93 Overpass
(looking northwest)
View of the completed Hoover Dam BOR Warehouse Old US 93 Overpass (Structure
H-2702).
High Resolution TIF (14 MB) |

Interchange Bridge (looking north)View of the completed
Hoover Dam Interchange Bridge (Structure H-2699).
High Resolution TIF (14 MB)
|

Canyon Bridge
(looking north)
View of the completed Hoover Dam Canyon Bridge (Structure H-2700) from Gold
Strike Canyon.
High Resolution TIF (14 MB) |

Nevada Interchange & Ramps (looking west)View of Nevada
Interchange and associated ramps, including the Hoover Dam Interchange Bridge
(Structure H-2699).
High Resolution TIF (14 MB)
|

Old US 93 Overpass
(looking northeast)
View of the completed Hoover Dam Old US 93 Overpass (Structure H-2703).
High Resolution TIF (14 MB) |
Return to the Top |
Images from September 2005 |
Colorado River Bridge...
|

Installing rock anchors. The photo one row below shows a more global picture
of where this work is actually being done. Two rows below, is a "bird's eye"
view of this work "area" (or ledge!).
(looking southeast)Ladd & Associates installing rock anchors at Pier 14 with
the aid of a Caterpillar 320C trackhoe.
High Resolution TIF (14 MB)
|

Excavation for Abutment 2
(looking north)View of the rock excavation for Abutment 2 footing (Arizona)
including the rock containment at the excavation face. Inverted orange cones
indicate drilled holes in preparation for blasting of the next lift.
High Resolution TIF (14 MB) |

Excavation work - look closely, you can see the work area for the men and
equipment shown in the first photo, at the row above.
(looking east)View of the future bridge alignment taken from Abutment 1
(Nevada) looking towards Abutment 2 (Arizona). Shown are the ongoing
excavations for Pier 14 (Arizona Skewback) and Abutment 2. In the
background of this picture, a crane is erecting the towers of the temporary
cableway crane which will span the canyon and be utilized for construction of
the bridge.
High Resolution TIF (14 MB)
|

Preparing to lift a segment of the crane tower
(looking west)Subcontractor, Olsen Beal, preparing for a lift of one segment
of the North temporary cableway crane tower. At completion, each tower
will rise 352-feet above the roadway elevation and will carry six 3-inch
diameter cables (3 each) 2,600 feet across the canyon.
High Resolution TIF (14 MB) |

Don't look down! Aerial view of Ladd & Associates installing rock anchors
for the backwall on Pier 14 (Arizona Skewback) looking down from a man basket
suspended above. Bottom right corner of this picture is the Colorado
River...approximately 650-feet below the level of this excavation.
High Resolution TIF (14 MB)
|

Future bridge alignment
(looking west)View of the future bridge alignment taken from Abutment 2
(Arizona) looking towards Abutment 1(Nevada). Shown are the on-going excavations
for Pier 5 (Nevada Skewback) and Pier 3; and completed footings of Piers 1 and
2. At the lower left of the picture, a crane located on Pier 15 lowers
personnel to the Pier 14 excavation (Arizona Skewback).
High Resolution TIF (14 MB) |
Nevada Approach...
|

Canyon Bridge (looking west)Foreground:
Edward Kraemer & Sons putting final finishes on the barrier railing of the
Hoover Dam Canyon Bridge (Structure H-2700).
Background: View of Nevada Interchange and associated ramps, including the
Hoover Dam Interchange Bridge (Structure H-2699).
High Resolution TIF (14 MB)
|

US 93 - new alignment
(looking west)
View of the completed US 93 alignment from Station 61+00 to 40+00 including the
Hoover Dam Interchange Bridge (Structure H-2699), Ramp D, MSE Wall 1, and the
Gold Strike Canyon Access Road.
High Resolution TIF (14 MB) |

In with the new, out with the old. (looking east)View of the completed US
93 alignment from Station 89+00 to 105+00 including the Hoover Dam Lower Portal
Access Road Overpass (Structure H-2701) and the Hoover Dam BOR Warehouse Old US
93 Overpass (Structure H-2702).
High Resolution TIF (14 MB)
|

Grading and compacting
(looking east)
KLB performing fine grading and compaction of embankment material for Ramp B, D
and the Gold Strike Canyon Access Road. The Hoover Dam Canyon Bridge
(Structure H-2700) appears in the upper right of this photo.
High Resolution TIF (14 MB) |
Return to the Top |
Images from August 2005 |
Colorado River Bridge...
|

Building bridge segments
(looking west)Obayashi / PSM, JV constructing precast segments for the Pier
columns at the precast yard located near Boulder City, Nevada.
High Resolution TIF (14 MB)
|

Stacking column segments
(looking east)
Obayashi / PSM, JV stacking precast column segments to verify casting and
alignment at the precast yard.
High Resolution TIF (14 MB) |

Rock containment work
(looking north)Ladd & Associates working from a man basket to construct rock
containment at Abutment 2.
High Resolution TIF (14 MB)
|

Future bridge alignment
(looking west)View of the future bridge alignment taken near Pier 5 (Nevada
Skewback) looking towards Abutment 1 (Nevada). Shown is the formwork for Pier 1
right, Pier 2 left/right, and pioneered access road into Pier 3.
High Resolution TIF (14 MB) |
Nevada Approach...
|

New US 93 Alignment (looking west)View of the new US 93 alignment from
Station 98+00 to 85+00 looking across the Hoover Dam Lower Portal Access Road
Overpass (Structure H-2701) bridge.
High Resolution TIF (14 MB)
|

Nevada Interchange & ramps
(looking northwest)
View of Nevada Interchange and associated ramps, including the Hoover Dam
Interchange Bridge (Structure H-2699) and the Gold Strike Canyon Access Road.
High Resolution TIF (14 MB) |

Old US 93 Overpass
(looking northeast)View of the Hoover Dam Old US 93 Overpass (Structure
H-2703) from the existing US 93.
High Resolution TIF (14 MB)
|

Loading & Hauling Excavated Material
(looking southwest)
KLB Construction loading and hauling excavated material from the US 93 alignment
near the Hoover Dam Old US 93 Overpass (Structure H-2703).
High Resolution TIF (14 MB) |
Return to the Top |
Images from July 2005 |
Colorado River Bridge...
|

Future bridge alignment
(looking west)View of the future bridge alignment taken from Abutment 2
(Arizona) looking towards Abutment 1 (Nevada). Shown is Ladd & Associates
drilling for blasting operations at Pier 5, the rock containment structure near
Pier 4 right, and constructed formwork for Piers 1 and 2 left footings.
High Resolution TIF
(14 MB)
|

Excavation with Link Belt TG1900 tower crane
(looking west)
Ladd & Associates removing blasted rock from the Pier 14 (Arizona Skewback)
excavation utilizing an 8 cubic yard bucket and the Link Belt TG1900 tower crane
erected on Pier 15 left footing.
High Resolution TIF (14 MB) |

Formwork for temporary footings
(looking west)Obayashi / PSM, JV constructing formwork for the temporary
cableway crane tower footings located in the Arizona alignment. Each
footing will utilize 200 cubic yards of concrete to construct.
High Resolution TIF (14 MB)
|

High Resolution TIF (14 MB) |

Nevada Skewback excavation
(looking east)
Foreground: Ladd & Associates preparing to excavate blasted rock from the Pier
5 (Nevada Skewback) excavation.
Background: View of Arizona side of the canyon showing Pier 14 (Arizona
Skewback), Pier 15 and Abutment 2 location along with the Link Belt TG1900 tower
crane erected on Pier 15 left footing.
High Resolution TIF (14 MB)
|

Link Belt TG1900 tower crane on Pier 15
(looking east)
View of the future bridge alignment taken from Pier 5 (Nevada Skewback) looking
towards Abutment 2 (Arizona). Shown is the Link Belt TG1900 tower crane
located on Pier 15 left footing. Ladd & Associates utilizing a trackhoe to
pioneer access to the top of Pier 15 right excavation.
High Resolution TIF (14 MB) |
Nevada Approach...
|

New US 93 Alignment (looking northeast)View of the new US 93 alignment
from Station 55+00 to 75+00 including the Hoover Dam Canyon Bridge (Structure
H-2700). A small portion of the Gold Strike Canyon Access Road appears in
the lower right of the photograph.
High Resolution TIF (14 MB)
|

Grading and Compacting on new US 93
(looking east)
Foreground: KLB Construction fine grading and compacting the final lift
on the constructed roadway embankment between Station 55+00 and 65+50.
Background: Edward Kraemer & Sons constructing barrier railing on the Hoover
Dam Canyon Bridge (Structure H-2700).
High Resolution TIF (14 MB) |

Nevada Interchange
(looking west)View of Nevada Interchange and associated ramps, including the
Hoover Dam Interchange Bridge (Structure H-2699) and the Gold Strike Canyon
Access Road.
High Resolution TIF (14 MB)
|

Old US 93 Overpass
(looking northeast)
View of the Hoover Dam Old US 93 Overpass (Structure H-2703) from the existing
US 93.
High Resolution TIF (14 MB) |

New US 93 and Canyon Bridge
(looking east)
View of the new US 93 alignment from Station 55+00 to 70+00 including the Hoover
Dam Canyon Bridge (Structure H-2700). KLB Construction fine grading and
compacting the final lift of the constructed roadway embankment.
High Resolution TIF (14 MB)
|

Nevada Interchange
(looking south)
View of Nevada Interchange and associated ramps, including the Hoover Dam
Interchange Bridge (Structure H-2699).
High Resolution TIF (14 MB) |
Return to the Top |
Images from June 2005 |
Colorado River Bridge... |

Ladd & Associates at work
(looking west)
Ladd & Associates, assembling the lattice boom section of a Link Belt TG1900
Tower Crane to be erected on the Pier 15 left footing.
High Resolution TIF (14 MB)
|

Assembling a Tower Crane
(looking east)
Ladd & Associates, assembling a Link Belt TG1900 Tower Crane on Pier 15 left
footing. This crane will be utilized to access and excavate Pier 14
(Arizona Skewback) and Pier 15 right.
High Resolution TIF (14 MB) |

Removing Temporary Access Road
(looking west)
Ladd & Associates removing temporary access road into Pier 2 area from Abutment
1.
High Resolution TIF (14 MB)
|

View of the Future Bridge Alignment
(looking east)
View of the future bridge alignment taken from Abutment 1 (Nevada) looking
towards Abutment 2 (Arizona). Pictured are the two Link Belt TG1900 tower
cranes, one on Pier 4 left footing and the other on Pier 15 left footing.
High Resolution TIF (14 MB) |

Obayashi / PSM, JV at work on Pier 1
(looking northeast)Obayashi / PSM, JV constructing formwork and setting grade
elevations for the Pier 1 left footing.
High Resolution TIF (14 MB)
|

Looking from Pier 5 to Pier 1
(looking southwest)
Aerial view of the new bridge alignment looking from Pier 5 (lower left) to
Pier 1 (mid right). The Nevada Hairpin of the existing US 93 appears at the
bottom of the photograph as it turns near the Link Belt TG1900 tower crane
erected on the Pier 4 left.
High Resolution TIF (14 MB) |
Nevada Approach... |

Edward Kraemer & Sons at work
(looking east)
Edward Kraemer & Sons placing concrete for the deck section of the Hoover Dam
Canyon Bridge (Structure H-2700).
High Resolution TIF (14 MB)
|

KLB Construction installing RCP pipe
(looking west)
KLB Construction installing RCP storm drainage pipe and drop inlets along the
centerline of the new US 93 alignment from Station 61+55 to 65+50.
High Resolution TIF (14 MB) |

View of Nevada Interchange
(looking east)
View of Nevada Interchange and associated ramps, including the Hoover Dam
Interchange Bridge (Structure H-2699).
High Resolution TIF (14 MB)
|

New US 93 Alignment
(looking east)
Foreground: KLB Construction loading blasted embankment material onto
haul trucks from the new roadway alignment near Station 122+00.
Background: Yenter Companies drilling in preparation for blasting operations
to excavate the roadway alignment near Station 123+50.
High Resolution TIF (14 MB) |

New US 93 alignment
(looking west)View of the new US 93 roadway alignment from Station 75+00 to
109+00, including the Hoover Dam Lower Portal Access Road Overpass (Structure
H-2701) and the Hoover Dam BOR Warehouse Old US 93 Overpass (Structure H-2702).
High Resolution TIF (14 MB)
|

New US 93 Alignment from Station 75+00 to 119+00
(looking southwest)
Top to Bottom: Hoover Dam Lower Portal Access Road Overpass (Structure
H-2701) and the Hoover Dam BOR Warehouse Old US 93 Overpass (Structure H-2702),
Hoover Dam Old US 93 Overpass (Structure H-2703) and the Nevada Security
Checkpoint location.
High Resolution TIF (14 MB) |
Return to the Top |
Images from May 2005 |
Colorado River Bridge... |

Ladd & Associates at work
(looking southwest)
Top Right: Ladd & Associates placing Shotcrete for the Special Rock Feature
reinforcement near Pier 1.
Middle Left: Ladd & Associates drilling in preparation for pioneering
blasting to gain access to the Pier 2 area from Abutment 1.
High Resolution TIF (14 MB)
|

Removing formwork from Pier 4
(looking west)
Obayashi / PSM, JV removing formwork from the recently placed concrete for Pier
4 Left footing. The crane is setting on the area to be excavated for Pier
5 near the Nevada Hairpin.
High Resolution TIF (14 MB) |

Arizona Side of the Canyon
(looking north)
View of the rock containment structures (fencing) near Abutment 2 on the Arizona
side of the canyon.
High Resolution TIF (14 MB)
|

Rock Containment Structures
(looking northwest)
Ladd & Associates constructing rock containment structures near Pier 15.
High Resolution TIF (14 MB) |

Arizona Side of the Canyon
(looking east)
Top: View of the Arizona side of the canyon showing Abutment 2 and pioneered
access road to Pier 15.
Bottom: Obayashi / PSM, JV removing formwork from the recently placed
concrete for Pier 4 Left footing.
High Resolution TIF (14 MB)
|

Ladd & Associates placing Shotcrete
(looking north)
Ladd & Associates placing Shotcrete for the Special Rock Feature reinforcement
near Pier 1on the Nevada side of the canyon.
High Resolution TIF (14 MB) |
Nevada Approach... |

New US 93 Alignment
(looking south)
View of the new US 93 alignment from Stations 26+93 to 75+00 including the
Nevada Interchange and associated ramps, including the Hoover Dam Interchange
Bridge (Structure H-2699) and the Hoover Dam Canyon Bridge (Structure H-2700).
High Resolution TIF (14 MB)
|

Existing US 93 Alignment
(looking northeast)
View of traffic on the existing US 93 as it passes through the falsework of the
newly constructed Hoover Dam Old US 93 Overpass (Structure H-2703).
High Resolution TIF (14 MB) |

Adjusting the Paving Machine
(looking west)
Edward Kraemer & Sons adjusting the Bidwell Paving Machine in preparation for
concrete placement for the deck section of the Hoover Dam Canyon Bridge
(Structure H-2700).
High Resolution TIF (14 MB)
|

Prepping for falsework removal
(looking southwest)
Foreground: Edward Kraemer & Sons setting up winches in preparation of
falsework removal on the newly constructed Hoover Dam Lower Portal Access Road
Overpass (Structure H-2701).
High Resolution TIF (14 MB) |

Lost Deck Formwork
(looking west)
View of the completed lost deck formwork on the Hoover Dam Old US 93 Overpass
(Structure H-2703).
High Resolution TIF (14 MB)
|

New US 93 Alignment
(looking east)
View of the new US 93 alignment from Stations 56+00 to 70+00 including the
Hoover Dam Canyon Bridge (Structure H-2700).
High Resolution TIF (14 MB) |
Return to the Top |
Images from April 2005 |
Breaking Ground for the Colorado River Bridge... |

Nevada Side of the Canyon
(looking west)
In this view of the Nevada side of the canyon, Ladd & Associates is shown
pioneering access to Abutment 1, Pier 1 and Pier 2.
Look closely at the bottom of the picture - the 3 white dashed lines on the
canyon wall indicate where the skewback foundations are to be constructed to
attach the bridge arch to the canyon wall.
High Resolution TIF (14 MB)
|

Rock Containment Structures
(looking southwest)
View of the rock containment structures (fencing) near Pier 1 and 2 on the
Nevada side of the canyon, prior to commencement of blasting operations.
High Resolution TIF (14 MB) |

Arizona Side of the Canyon
(looking east)
Ladd & Associates pioneering access to Abutment 2 and Pier 15 from the Arizona
side of the canyon. Constructed rock containment structures appear near
the bottom right of the picture.
High Resolution TIF (14 MB)
|

Pioneering Access to Abutment and Piers
(looking west)
Ladd & Associates pioneering access to Abutment 1, Pier 1 and Pier 2 from the
Nevada side of the canyon. Constructed rock containment structures appear
near the bottom the the picture.
High Resolution TIF (14 MB) |

New US 93
(looking south)
View of the new US 93 alignment from station 197+65 to 206+00 including the
Sugarloaf Mountain rock cut and the staging area for the earthworks
subcontractor, Ladd & Associates.
High Resolution TIF (14 MB)
|

New US 93 Alignment
(looking south)
View of new US 93 alignment from station 170+00 to 177+00 including the staging
area for the earthworks subcontractor, Ladd & Associates.
High Resolution TIF (14 MB) |
The Nevada Approach is nearly 90% complete! |

Lower Portal Access Road Overpass
(looking southwest)
Edward Kraemer & Sons removing curing blankets from the recently constructed
deck of the Hoover Dam Lower Portal Access Road Overpass
(Structure H-2701).
High Resolution TIF (14 MB)
|

Old US 93 Overpass
(looking west)
View of Edward Kraemer & Sons constructing formwork for the girder sections at
the Hoover Dam Old US 93 Overpass (Structure H-2703).
High Resolution TIF (14 MB) |

Canyon Bridge
(looking east)
Edward Kraemer & Sons completing placement of stay-in-place formwork and
Paradise Rebar placing reinforcing steel for the deck of the Hoover Dam Canyon
Bridge (Structure H-2700).
High Resolution TIF (14 MB)
|

New US 93 Alignment
(looking southwest)
View of the new US 93 alignment from stations 76+00 to 110+00 including the
Hoover Dam Lower Portal Access Road Overpass (Structure H-2701) and the Hoover
Dam BOR Warehouse Old US 93 Overpass (Structure H-2702).
High Resolution TIF (14 MB) |

Nevada Interchange and New US 93 Alignment
(looking west)
View of the new US 93 alignment from stations 26+93 to 75+00 including the
Nevada Interchange and associated ramps, also including the Hoover Dam
Interchange Bridge (Structure H-2699) and the Hoover Dam Canyon Bridge
(Structure H-2700).
High Resolution TIF (14 MB)
|

Nevada Interchange and Ramps
(looking west)
View of the Nevada Interchange and associated ramps, including the Hoover Dam
Interchange Bridge (Structure H-2699).
High Resolution TIF (14 MB) |
Return to the Top |
Images from March 2005 |
Interchange and Overpass
- Bridges on the Nevada side take shape... |

Nevada Interchange
(looking southeast)
View of Nevada Interchange and associated ramps, including the Hoover Dam
Interchange Bridge (Structure H-2699).
High Resolution TIF (14 MB)
|

Hoover Dam Interchange Bridge
(looking north)
View of completed Hoover Dam Interchange Bridge (Structure H-2699) looking from
the Gold Strike Canyon Access Road.
High Resolution TIF (14 MB) |

Hoover Dam Canyon Bridge Pier
(looking northeast)
Edward Kraemer & Sons torque bolts at the connections of the structural steel
girders for the Hoover Dam Canyon Bridge (Structure H-2700) from Pier 1 to Pier
2.
High Resolution TIF (14 MB)
|

Steel Girders of the Canyon Bridge
(looking west)
View of the completed structural steel girders for the Hoover Dam Canyon Bridge
(Structure H-2700) looking from Abutment 2 towards Abutment 1.
High Resolution TIF (14 MB) |

Post Tensioning Ductwork
(looking northwest)
Paradise Rebar placing post tensioning ductwork for the girder sections at the
Hoover Dam Old US93 Overpass (Structure H-2703).
High Resolution TIF (14 MB)
|

Formwork on Lower Portal Access Road Overpass
(looking southwest)
Foreground: Edward Kraemer & Sons constructing lost deck formwork for
the Hoover Dam Lower Portal Access Road Overpass (Structure H-2701).
Background: View of placed embankment fill from US93 station 85+00 to 94+76.
High Resolution TIF (14 MB) |
Return to the Top |
Images from February 2005 |
Nevada Approach: Setting the
Girders... |

Nevada Interchange
(looking west)
View of Nevada Interchange and associated ramps, including the Hoover Dam
Interchange Bridge (Structure H-2699).
High Resolution TIF (14 MB)
|

Hoover Dam Canyon Bridge
(looking northeast)
Edward Kraemer & Sons placing the structural steel girders for the Hoover Dam
Canyon Bridge (Structure H-2700) from Pier 1 to Pier 2.
High Resolution TIF (14 MB) |

Barrier Fencing
(looking north)
LS Fence constructing wildlife and tortoise barrier fencing.
High Resolution TIF (14 MB)
|

Hoover Dam Canyon Bridge
(looking north)
Edward Kraemer & Sons placing the structural steel girders for the Hoover Dam
Canyon Bridge (Structure H-2700) from Abutment 1 to Pier 1.
High Resolution TIF (14 MB) |

Canyon Bridge
(looking northeast)
View of the partially completed substructure of the Hoover Dam Canyon Bridge
(Structure H-2700) and roadway alignment from Station 60+00 to 80+00.
High Resolution TIF (14 MB)
|

Mechanically Stabilized Earth Wall 2
(looking northwest)
View of completed Mechanically Stabilized Earth Wall 2 along the right side of
Ramp D from Station 102+44 to Station 111+74 prior to application of the
weathering agent (rock staining).
High Resolution TIF (14 MB) |

Lower Portal Access Road Overpass
(looking southwest)
Foreground: Edward Kraemer & Sons constructing formwork for the girders
of the Hoover Dam Lower Portal Access Road Overpass (Structure H-2701).
Background: KLB Construction placing embankment fill from US 93 Station 85+00
to 94+76.
High Resolution TIF (14 MB) |
Return to the Top |
Images from January 2005 |
Nevada Approach: Building into a new year... |

Canyon Bridge
(looking northwest)
Foreground: Edward Kraemer & Sons constructing
formwork for Abutment 2 of the Hoover Dam
Canyon Bridge (Structure H-2700).
Center: View of Pier 2 in construction and the completed Pier 1 of the Hoover
Dam Canyon Bridge.
Background: View of the formwork placement for Abutment 1 of the Hoover Dam
Canyon Bridge.
High Resolution TIF (14 MB)
|

Pier 2 - Hoover Dam Canyon Bridge
(looking northwest)
Paradise Rebar placing reinforcing steel for construction of Pier 2 (right) on
the Hoover Dam Canyon Bridge (Structure H-2700).
High Resolution TIF(14 MB) |

Old US 93 Overpass
(looking west)
Center right: View of the completed Abutment 1 Bearing Seat at the Hoover Dam
Old US 93 Overpass (Structure H-2703).
Center left: KLB Construction placing fill material to construct the US 93
alignment from Stations 110+00 to 115+00.
High Resolution TIF (14 MB)
|

Hoover Dam Canyon Bridge
(looking north)
Center left: View of the US 93 alignment from Station 60+00 to 65+00.
Center right: Edward Kraemer & Sons constructing
the Hoover Dam Canyon Bridge (Structure H-2700).
High Resolution TIF(14 MB) |

New US 93 Alignment
(looking southwest)
View of the completed US 93 alignment from Station 177+00 to Station 170+00.
High Resolution TIF (14 MB)
|

Lower Portal Access Road Overpass
(looking southwest)
Foreground: View of reinforcing steel, formwork, and post tensioning duct
placement for construction of the Hoover Dam Lower Portal Access Road Overpass
(Structure H-2701).
Background: View of the embankment fill for construction of the US 93
alignment from Station 71+00 to Station 95+00.
High Resolution TIF(14 MB) |
Return to the Top |
Additional Photos/Images of the Hoover Dam Bypass Project
If you would like to see
renderings of what we expect the final project to look like, please see our
other
Photo Gallery.
If you would like to see
construction photos of the Arizona Approach (Mid-2003 to November 2004), please
use this link:
Arizona Approach Photos
If you would like to see
earlier photos of the Nevada Approach (construction prior to January 2005),
please use this link:
Nevada Approach Photos
To view real-time images of
construction on the Colorado River bridge, please see our
Hoover Dam Bypass Webcam.
|
|
Back to Construction
Activities |
|